Implementation of modeling and simulation in semiconductor wafer fabrication with time constraints between wet etch and furnace operations

Wolfgang Scholl, Joerg Domaschke

Open publisher page 84 citations

Abstract

In semiconductor wafer fabrication, time constraints between process steps in furnace and wet etch make it difficult to achieve cycle time targets and maximize machine utilization. For capacity planning, it is difficult to estimate the impact of these time constraints on the machine capacity. Infineon Technologies Dresden has conducted a study using discrete event simulation, to investigate the actual situation in the factory and to identify recommendations to eliminate or to reduce the impart of time constraints. The work in this paper yields a two-day reduction in total cycle time after implementation of findings in the factory.

About this research paper

What this paper is about

In semiconductor wafer fabrication, time constraints between process steps in furnace and wet etch make it difficult to achieve cycle time targets and maximize machine utilization. For capacity planning, it is difficult to estimate the impact of these time constraints on the machine capacity. Infineon Technologies Dresden has conducted a study using discrete event simulation, to investigate the actual situation in the factory and to identify recommendations to eliminate or to reduce the impart of time constraints. The work in this paper yields a two-day reduction in total cycle time after implementation of findings in the factory.

Why it matters

OpenAlex reports 84 citations for this work. Citation counts describe recorded attention and do not establish research quality.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

In semiconductor wafer fabrication, time constraints between process steps in furnace and wet etch make it difficult to achieve cycle time targets and maximize machine utilization. For capacity planning, it is difficult to estimate the impact of these time constraints on the machine capacity. Infineon Technologies Dresden has conducted a study using discrete event simulation, to investigate the actual situation in the factory and to identify recommendations to eliminate or to reduce the impart of time constraints. The work in this paper yields a two-day reduction in total cycle time after implementation of findings in the factory.

Key concepts: Wafer fabrication, Semiconductor device fabrication, Factory (object-oriented programming), Wafer, Engineering, Process (computing), Reduction (mathematics), Reliability engineering

Related papers

Back to paper searchBrowse research topicsOriginal source
Implementation of modeling and simulation in semiconductor wafer fabrication with time constraints between wet etch and furnace operations — Research Paper | ScholarLens