To evaluate the effectiveness of Section XI, Division 1, {open_quotes}Rules for Inservice Inspection of Nuclear Power Plant Components,{close_quotes} of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, searches were performed of the Licensing Event Report and Nuclear Plant Reliability Data System computerized data bases, and a review was made of inservice inspection summary reports. It was found that the Section XI examinations and tests detect flaws in welds and plant components and result in subsequent corrective action. This study also shows that the format and topics of information provided in Section XI-prescribed inservice inspection summary reports vary widely.

About this research paper

What this paper is about

To evaluate the effectiveness of Section XI, Division 1, {open_quotes}Rules for Inservice Inspection of Nuclear Power Plant Components,{close_quotes} of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, searches were performed of the Licensing Event Report and Nuclear Plant Reliability Data System computerized data bases, and a review was made of inservice inspection summary reports. It was found that the Section XI examinations and tests detect flaws in welds and plant components and result in subsequent corrective action. This study also shows that the format and topics of information provided in Section XI-prescribed inservice inspection summary reports vary widely.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

To evaluate the effectiveness of Section XI, Division 1, {open_quotes}Rules for Inservice Inspection of Nuclear Power Plant Components,{close_quotes} of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, searches were performed of the Licensing Event Report and Nuclear Plant Reliability Data System computerized data bases, and a review was made of inservice inspection summary reports. It was found that the Section XI examinations and tests detect flaws in welds and plant components and result in subsequent corrective action. This study also shows that the format and topics of information provided in Section XI-prescribed inservice inspection summary reports vary widely.

Key concepts: Section (typography), Nuclear power plant, Code of practice, Code (set theory), Boiler (water heating), Engineering, Computer science, Forensic engineering

Related papers

Back to paper searchBrowse research topicsOriginal source
Review of Section XI inservice inspection program effectiveness — Research Paper | ScholarLens