Contracting and Project Management of Complex Equipment

R. B. Jones

Open publisher page 0 citations

Abstract

As the sole builder of nuclear aircraft carriers for the U.S. Navy, Northrop Grumman Newport News relies heavily on the 900-metric-ton Goliath gantry crane to assembly the 162 critical "super lifts" that compose a completed carrier structure. Prior to 1999, it was apparent that the 25-year-old crane needed a major overhaul. When the project was funded in 1999, Newport News assembled a team composed of engineering, maintenance, and operations to perform detailed design, develop the specification, manage the bidding process, and manage the project. Capital constraints on the project required the team to collaborate with suppliers to move portions of the project scope back to Newport News, reducing risk for the suppliers and reducing capital costs for Newport News. This team/collaboration approach proved successful as the project was completed on schedule and within budget.

About this research paper

What this paper is about

As the sole builder of nuclear aircraft carriers for the U.S. Navy, Northrop Grumman Newport News relies heavily on the 900-metric-ton Goliath gantry crane to assembly the 162 critical "super lifts" that compose a completed carrier structure. Prior to 1999, it was apparent that the 25-year-old crane needed a major overhaul. When the project was funded in 1999, Newport News assembled a team composed of engineering, maintenance, and operations to perform detailed design, develop the specification, manage the bidding process, and manage the project. Capital constraints on the project required the team to collaborate with suppliers to move portions of the project scope back to Newport News, reducing risk for the suppliers and reducing capital costs for Newport News. This team/collaboration approach proved successful as the project was completed on schedule and within budget.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

As the sole builder of nuclear aircraft carriers for the U.S. Navy, Northrop Grumman Newport News relies heavily on the 900-metric-ton Goliath gantry crane to assembly the 162 critical "super lifts" that compose a completed carrier structure. Prior to 1999, it was apparent that the 25-year-old crane needed a major overhaul. When the project was funded in 1999, Newport News assembled a team composed of engineering, maintenance, and operations to perform detailed design, develop the specification, manage the bidding process, and manage the project. Capital constraints on the project required the team to collaborate with suppliers to move portions of the project scope back to Newport News, reducing risk for the suppliers and reducing capital costs for Newport News. This team/collaboration approach proved successful as the project was completed on schedule and within budget.

Key concepts: Schedule, Bidding, Navy, Scope (computer science), Engineering, Project management, Engineering management, Project team