Top Ten CPM Scheduling Mistakes

Amon Ackley, J. Wesley Baker, Scott A. Lowe

Open publisher page 2 citations

Abstract

As experts on construction delays and presenters of critical path method (CPM) training, the authors of this paper regularly get the opportunity to review a variety of project schedules. What the authors find is that good schedules are essential to reliably completing construction projects profitably and on time. If they’re used, they make every project manager better, even those that think they don’t need a CPM schedule. A good schedule provides other benefits. It allows time to be measured accurately. That means agencies and contractors don’t have to fight about the delay associated with a change. They can accurately evaluate the time lost to a problem and determine the time extension due, if any, when the problem occurs; they don’t end up waiting until the end of the project and dealing with the problem as a claim. In fact, not only is a good schedule a good way to measure delays, in many contracts, it’s often the only way to measure time and prove entitlement to a time extension. As one federal judge said, “The parties will ‘live or die’ by the contemporaneous project schedule.” The problem arises when the CPM schedule put together for the project doesn’t accurately communicate or doesn’t accurately match the contractor’s plan. Many contracts require CPM schedules and when they don’t, many contractors have been convinced of their effectiveness and use them anyway. After looking at hundreds of schedules on almost every conceivable type of project we have compiled a list of common mistakes. These mistakes hurt a project in at least two ways. First, because the CPM schedule is, or should be, used to administer the work, mistakes may cause the project team to focus resources in the wrong place at the wrong time, or prevent the parties from accurately assessing whether the job is ahead or behind schedule. This potentially reduces everyone’s efficiency, increases costs, and reduces profits. Second, if there is a delay that leads to a dispute, the errors in the schedule may lead to disagreements and claims regarding what work activities actually delayed the project and by how much. In today’s construction environment one of the most daunting risks faced by the project team is delay. While owners and contractors both recognize the costs of delay, and agonize over the specter of litigation, delays can be avoided or quickly and amicably resolved through the use of good scheduling practices.

About this research paper

What this paper is about

As experts on construction delays and presenters of critical path method (CPM) training, the authors of this paper regularly get the opportunity to review a variety of project schedules. What the authors find is that good schedules are essential to reliably completing construction projects profitably and on time. If they’re used, they make every project manager better, even those that think they don’t need a CPM schedule. A good schedule provides other benefits. It allows time to be measured accurately. That means agencies and contractors don’t have to fight about the delay associated with a change. They can accurately evaluate the time lost to a problem and determine the time extension due, if any, when the problem occurs; they don’t end up waiting until the end of the project and dealing with the problem as a claim. In fact, not only is a good schedule a good way to measure delays, in many contracts, it’s often the only way to measure time and prove entitlement to a time extension. As one federal judge said, “The parties will ‘live or die’ by the contemporaneous project schedule.” The problem arises when the CPM schedule put together for the project doesn’t accurately communicate or doesn’t accurately match the contractor’s plan. Many contracts require CPM schedules and when they don’t, many contractors have been convinced of their effectiveness and use them anyway. After looking at hundreds of schedules on almost every conceivable type of project we have compiled a list of common mistakes. These mistakes hurt a project in at least two ways. First, because the CPM schedule is, or should be, used to administer the work, mistakes may cause the project team to focus resources in the wrong place at the wrong time, or prevent the parties from accurately assessing whether the job is ahead or behind schedule. This potentially reduces everyone’s efficiency, increases costs, and reduces profits. Second, if there is a delay that leads to a dispute, the errors in the schedule may lead to disagreements and claims regarding what work activities actually delayed the project and by how much. In today’s construction environment one of the most daunting risks faced by the project team is delay. While owners and contractors both recognize the costs of delay, and agonize over the specter of litigation, delays can be avoided or quickly and amicably resolved through the use of good scheduling practices.

Why it matters

OpenAlex reports 2 citations for this work. Citation counts describe recorded attention and do not establish research quality.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

As experts on construction delays and presenters of critical path method (CPM) training, the authors of this paper regularly get the opportunity to review a variety of project schedules. What the authors find is that good schedules are essential to reliably completing construction projects profitably and on time. If they’re used, they make every project manager better, even those that think they don’t need a CPM schedule. A good schedule provides other benefits. It allows time to be measured accurately. That means agencies and contractors don’t have to fight about the delay associated with a change. They can accurately evaluate the time lost to a problem and determine the time extension due, if any, when the problem occurs; they don’t end up waiting until the end of the project and dealing with the problem as a claim. In fact, not only is a good schedule a good way to measure delays, in many contracts, it’s often the only way to measure time and prove entitlement to a time extension. As one federal judge said, “The parties will ‘live or die’ by the contemporaneous project schedule.” The problem arises when the CPM schedule put together for the project doesn’t accurately communicate or doesn’t accurately match the contractor’s plan. Many contracts require CPM schedules and when they don’t, many contractors have been convinced of their effectiveness and use them anyway. After looking at hundreds of schedules on almost every conceivable type of project we have compiled a list of common mistakes. These mistakes hurt a project in at least two ways. First, because the CPM schedule is, or should be, used to administer the work, mistakes may cause the project team to focus resources in the wrong place at the wrong time, or prevent the parties from accurately assessing whether the job is ahead or behind schedule. This potentially reduces everyone’s efficiency, increases costs, and reduces profits. Second, if there is a delay that leads to a dispute, the errors in the schedule may lead to disagreements and claims regarding what work activities actually delayed the project and by how much. In today’s construction environment one of the most daunting risks faced by the project team is delay. While owners and contractors both recognize the costs of delay, and agonize over the specter of litigation, delays can be avoided or quickly and amicably resolved through the use of good scheduling practices.

Key concepts: Schedule, Critical path method, Computer science, Operations research, Plan (archaeology), Project management, Scheduling (production processes), Variety (cybernetics)