Research on Stability in Metro Tunnel Constructing with Shallow Buried Covered Excavation in Loose Sand Layers

Shen Gang Li, Zhao Wen, Xiao-Li Cai, Yin Fu, Lu Zhang

Open full text 0 citations

Abstract

For subway tunneling in urban underground, high safty of construction is needed.However, the safty and rationality of excavating plan are forecasted difficultly because of consealment. Based on the Zhang-Shen tunnel construction of Shenyang subway, bench method, single side-wall heading excavation method and CD excavation method are numerical simulated; according to the numerical calculation results and the constructing process, bench method is adopted; the ground settlement caused by excavation monitored during excavating is in the allowed range and the tunnel is safe during excavating.

About this research paper

What this paper is about

For subway tunneling in urban underground, high safty of construction is needed.However, the safty and rationality of excavating plan are forecasted difficultly because of consealment. Based on the Zhang-Shen tunnel construction of Shenyang subway, bench method, single side-wall heading excavation method and CD excavation method are numerical simulated; according to the numerical calculation results and the constructing process, bench method is adopted; the ground settlement caused by excavation monitored during excavating is in the allowed range and the tunnel is safe during excavating.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

For subway tunneling in urban underground, high safty of construction is needed.However, the safty and rationality of excavating plan are forecasted difficultly because of consealment. Based on the Zhang-Shen tunnel construction of Shenyang subway, bench method, single side-wall heading excavation method and CD excavation method are numerical simulated; according to the numerical calculation results and the constructing process, bench method is adopted; the ground settlement caused by excavation monitored during excavating is in the allowed range and the tunnel is safe during excavating.

Key concepts: Excavation, Settlement (finance), Engineering, Geotechnical engineering, Plan (archaeology), Heading (navigation), Range (aeronautics), Civil engineering