A Model for Assessing Maximum Overtime Rate in Labor Subcontracting Practices

Khaled Nassar, Ossama Hosny

Open full text 3 citations

Abstract

Despite the rapid development in the construction industry due to the changing new technologies, many projects still fail to meet target deadlines. Shortage in manpower and skilled laborers is one of the main reasons for such delays. Markets with high economic growth and economic expansion (such as Gulf Countries in the Middle East) may have pronounced labor the shortages. Labor subcontracting practices are used sometimes to increase production rates and meet project deadlines. This paper explains and analyses labor subcontracting practices currently being used in many places around the world (and especially in the Gulf Countries) and in particular defines a maximum overtime rate for laborers in the laborer-subcontracting method ensuring that the contractor gains both the time saved during overtime and also reduces the cost per unit produced. The mathematical model used formalizes a closed-form equation for overtime pay in similar situations and as such can be applicable worldwide. Data was collected from representative projects that employed such practices from various trades. Validation of the model and formula has been tested successfully by analyzing historic data. The results prove that contractors often do not reach the optimum use of their practices resulting in a higher cost per unit. The presented model and the analysis should be of interest to many contractors currently involved in the practice or considering its use and to those who wish to find new methods that would help in eliminating as much wastes as possible by allocating their resources in the most efficient way.

Open-access reader

About this research paper

What this paper is about

Despite the rapid development in the construction industry due to the changing new technologies, many projects still fail to meet target deadlines. Shortage in manpower and skilled laborers is one of the main reasons for such delays. Markets with high economic growth and economic expansion (such as Gulf Countries in the Middle East) may have pronounced labor the shortages. Labor subcontracting practices are used sometimes to increase production rates and meet project deadlines. This paper explains and analyses labor subcontracting practices currently being used in many places around the world (and especially in the Gulf Countries) and in particular defines a maximum overtime rate for laborers in the laborer-subcontracting method ensuring that the contractor gains both the time saved during overtime and also reduces the cost per unit produced. The mathematical model used formalizes a closed-form equation for overtime pay in similar situations and as such can be applicable worldwide. Data was collected from representative projects that employed such practices from various trades. Validation of the model and formula has been tested successfully by analyzing historic data. The results prove that contractors often do not reach the optimum use of their practices resulting in a higher cost per unit. The presented model and the analysis should be of interest to many contractors currently involved in the practice or considering its use and to those who wish to find new methods that would help in eliminating as much wastes as possible by allocating their resources in the most efficient way.

Why it matters

OpenAlex reports 3 citations for this work. Citation counts describe recorded attention and do not establish research quality.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

Despite the rapid development in the construction industry due to the changing new technologies, many projects still fail to meet target deadlines. Shortage in manpower and skilled laborers is one of the main reasons for such delays. Markets with high economic growth and economic expansion (such as Gulf Countries in the Middle East) may have pronounced labor the shortages. Labor subcontracting practices are used sometimes to increase production rates and meet project deadlines. This paper explains and analyses labor subcontracting practices currently being used in many places around the world (and especially in the Gulf Countries) and in particular defines a maximum overtime rate for laborers in the laborer-subcontracting method ensuring that the contractor gains both the time saved during overtime and also reduces the cost per unit produced. The mathematical model used formalizes a closed-form equation for overtime pay in similar situations and as such can be applicable worldwide. Data was collected from representative projects that employed such practices from various trades. Validation of the model and formula has been tested successfully by analyzing historic data. The results prove that contractors often do not reach the optimum use of their practices resulting in a higher cost per unit. The presented model and the analysis should be of interest to many contractors currently involved in the practice or considering its use and to those who wish to find new methods that would help in eliminating as much wastes as possible by allocating their resources in the most efficient way.

Key concepts: Overtime, Economic shortage, Unit (ring theory), Business, Labor cost, Unit price, Production (economics), Economics