Changes in the unit price of work for reinforced concrete construction based on building sites

Mubarak Mubarak, Abdullah Abdullah, Medyan Riza, Yulia Hayati

Open full text 3 citations

Abstract

Abstract The unit price of work is the price required to complete each unit of quantity of work that consists of the unit price for the wage of labour, materials, and equipment used. Changes in unit prices are possibly determined by the different sites in which a building is constructed. For budget planners or construction executors, a good understanding of the changes in the unit price of work is required to identify the reasonable amount of budget needed. Given these circumstances, this study was conducted to analyse and identify the pattern of changes in the unit price of work based on the locations of a building in the Province of Aceh. This research focuses on the unit price of reinforced concrete work for the building structure components, as the work that has the most significant proportion of cost in building construction. The pattern of change is described in the form of price indexes by applying the price in Banda Aceh City as a reference for other cities/districts. The analysis results in two patterns of the unit price index, which is below or above of the reference index. This condition follows the pattern of the unit price of materials and wages. The ease of access to a region also determine the changes in the price index.

Open-access reader

About this research paper

What this paper is about

Abstract The unit price of work is the price required to complete each unit of quantity of work that consists of the unit price for the wage of labour, materials, and equipment used. Changes in unit prices are possibly determined by the different sites in which a building is constructed. For budget planners or construction executors, a good understanding of the changes in the unit price of work is required to identify the reasonable amount of budget needed. Given these circumstances, this study was conducted to analyse and identify the pattern of changes in the unit price of work based on the locations of a building in the Province of Aceh. This research focuses on the unit price of reinforced concrete work for the building structure components, as the work that has the most significant proportion of cost in building construction. The pattern of change is described in the form of price indexes by applying the price in Banda Aceh City as a reference for other cities/districts. The analysis results in two patterns of the unit price index, which is below or above of the reference index. This condition follows the pattern of the unit price of materials and wages. The ease of access to a region also determine the changes in the price index.

Why it matters

OpenAlex reports 3 citations for this work. Citation counts describe recorded attention and do not establish research quality.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

Abstract The unit price of work is the price required to complete each unit of quantity of work that consists of the unit price for the wage of labour, materials, and equipment used. Changes in unit prices are possibly determined by the different sites in which a building is constructed. For budget planners or construction executors, a good understanding of the changes in the unit price of work is required to identify the reasonable amount of budget needed. Given these circumstances, this study was conducted to analyse and identify the pattern of changes in the unit price of work based on the locations of a building in the Province of Aceh. This research focuses on the unit price of reinforced concrete work for the building structure components, as the work that has the most significant proportion of cost in building construction. The pattern of change is described in the form of price indexes by applying the price in Banda Aceh City as a reference for other cities/districts. The analysis results in two patterns of the unit price index, which is below or above of the reference index. This condition follows the pattern of the unit price of materials and wages. The ease of access to a region also determine the changes in the price index.

Key concepts: Unit price, Unit (ring theory), Work (physics), Price index, Index (typography), Producer price index, Wage, Price level

Related papers

Back to paper searchBrowse research topicsOriginal source
Changes in the unit price of work for reinforced concrete construction based on building sites — Research Paper | ScholarLens