Impact of Partial Bridge Raising on Post-Tensioned Steel Plate Girder Bridge

Mike Wongkaew, Matt Miller

Open publisher page 0 citations

Abstract

The 1378-ft-long, 10-span continuous Kootenai River Bridge in Bonner's Ferry, Idaho is a rare example of composite design utilizing a prestressed concrete deck and steel plate girders. Through the use of transverse and longitudinal post-tensioning in the cast-in-place deck, a minimum girder spacing of 18 ft was achieved. Additionally, this structure was constructed in the early 1980's without any interior expansion joints, accommodating all longitudinal movement at the bridge ends via finger plate expansion joints. The functionality of the expansion joints and the condition of the bridge's pot bearings were investigated in 2004. Although the bridge superstructure and substructure were in satisfactory condition, some of the bearings required replacement as a result of deterioration due to exposure to the elements and leakage through the expansion joint. In order to facilitate removal and replacement of the deteriorated bearings, the superstructure required raising. It was infeasible to raise the entire bridge, requiring that the bridge be raised partially (i.e. differentially) which led to distortion of the bridge cross section. A series of finite element analyses were performed to investigate the stress changes and total stresses due to various bridge partial raising scenarios. Strengthening plans were subsequently developed for structural elements that would be subject to higher demands than their capacities. Where members could not be practically strengthened, analyses could be used as a tool to determine the allowable differential jacking heights. The finite element analyses also provided reactions at various supports, which were then used to develop requirements for jacks and jacking stiffeners. Construction was completed in 2008. This paper presents the analytical technique used to investigate the impact of partial raising on the composite post-tensioned concrete deck, steel plate girder bridge and discusses lessons learned during the course of design and construction.

About this research paper

What this paper is about

The 1378-ft-long, 10-span continuous Kootenai River Bridge in Bonner's Ferry, Idaho is a rare example of composite design utilizing a prestressed concrete deck and steel plate girders. Through the use of transverse and longitudinal post-tensioning in the cast-in-place deck, a minimum girder spacing of 18 ft was achieved. Additionally, this structure was constructed in the early 1980's without any interior expansion joints, accommodating all longitudinal movement at the bridge ends via finger plate expansion joints. The functionality of the expansion joints and the condition of the bridge's pot bearings were investigated in 2004. Although the bridge superstructure and substructure were in satisfactory condition, some of the bearings required replacement as a result of deterioration due to exposure to the elements and leakage through the expansion joint. In order to facilitate removal and replacement of the deteriorated bearings, the superstructure required raising. It was infeasible to raise the entire bridge, requiring that the bridge be raised partially (i.e. differentially) which led to distortion of the bridge cross section. A series of finite element analyses were performed to investigate the stress changes and total stresses due to various bridge partial raising scenarios. Strengthening plans were subsequently developed for structural elements that would be subject to higher demands than their capacities. Where members could not be practically strengthened, analyses could be used as a tool to determine the allowable differential jacking heights. The finite element analyses also provided reactions at various supports, which were then used to develop requirements for jacks and jacking stiffeners. Construction was completed in 2008. This paper presents the analytical technique used to investigate the impact of partial raising on the composite post-tensioned concrete deck, steel plate girder bridge and discusses lessons learned during the course of design and construction.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

The 1378-ft-long, 10-span continuous Kootenai River Bridge in Bonner's Ferry, Idaho is a rare example of composite design utilizing a prestressed concrete deck and steel plate girders. Through the use of transverse and longitudinal post-tensioning in the cast-in-place deck, a minimum girder spacing of 18 ft was achieved. Additionally, this structure was constructed in the early 1980's without any interior expansion joints, accommodating all longitudinal movement at the bridge ends via finger plate expansion joints. The functionality of the expansion joints and the condition of the bridge's pot bearings were investigated in 2004. Although the bridge superstructure and substructure were in satisfactory condition, some of the bearings required replacement as a result of deterioration due to exposure to the elements and leakage through the expansion joint. In order to facilitate removal and replacement of the deteriorated bearings, the superstructure required raising. It was infeasible to raise the entire bridge, requiring that the bridge be raised partially (i.e. differentially) which led to distortion of the bridge cross section. A series of finite element analyses were performed to investigate the stress changes and total stresses due to various bridge partial raising scenarios. Strengthening plans were subsequently developed for structural elements that would be subject to higher demands than their capacities. Where members could not be practically strengthened, analyses could be used as a tool to determine the allowable differential jacking heights. The finite element analyses also provided reactions at various supports, which were then used to develop requirements for jacks and jacking stiffeners. Construction was completed in 2008. This paper presents the analytical technique used to investigate the impact of partial raising on the composite post-tensioned concrete deck, steel plate girder bridge and discusses lessons learned during the course of design and construction.

Key concepts: Expansion joint, Structural engineering, Girder, Deck, Raising (metalworking), Bridge (graph theory), Engineering, Substructure

Related papers

Back to paper searchBrowse research topicsOriginal source
Impact of Partial Bridge Raising on Post-Tensioned Steel Plate Girder Bridge — Research Paper | ScholarLens