In order to study the vertical displacement distribution of foundation pit in the process of step-by-step excavation, combined with a foundation pit project, numerical simulation analysis with finite element software was carried in the research. The results show that: in the process of excavation, the maximum settlement of soil outside the pit is 41.4 mm, which is 2.95 ‰ of pit excavation depth and conforms to the recommended value in specifications. The maximum vertical displacement of soil at the bottom of foundation pit is in the center of pit. Its value is gradually increasing with the excavation, and the maximum is 60.1 mm, which is 4.32 ‰ of foundation pit depth,also,it conforms to the specifications proposed value. The proposed scheme can satisfy the vertical displacement of foundation pit excavation in the construction process.

About this research paper

What this paper is about

In order to study the vertical displacement distribution of foundation pit in the process of step-by-step excavation, combined with a foundation pit project, numerical simulation analysis with finite element software was carried in the research. The results show that: in the process of excavation, the maximum settlement of soil outside the pit is 41.4 mm, which is 2.95 ‰ of pit excavation depth and conforms to the recommended value in specifications. The maximum vertical displacement of soil at the bottom of foundation pit is in the center of pit. Its value is gradually increasing with the excavation, and the maximum is 60.1 mm, which is 4.32 ‰ of foundation pit depth,also,it conforms to the specifications proposed value. The proposed scheme can satisfy the vertical displacement of foundation pit excavation in the construction process.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

In order to study the vertical displacement distribution of foundation pit in the process of step-by-step excavation, combined with a foundation pit project, numerical simulation analysis with finite element software was carried in the research. The results show that: in the process of excavation, the maximum settlement of soil outside the pit is 41.4 mm, which is 2.95 ‰ of pit excavation depth and conforms to the recommended value in specifications. The maximum vertical displacement of soil at the bottom of foundation pit is in the center of pit. Its value is gradually increasing with the excavation, and the maximum is 60.1 mm, which is 4.32 ‰ of foundation pit depth,also,it conforms to the specifications proposed value. The proposed scheme can satisfy the vertical displacement of foundation pit excavation in the construction process.

Key concepts: Excavation, Foundation (evidence), Geotechnical engineering, Displacement (psychology), Settlement (finance), Engineering, Vertical displacement, Finite element method

Related papers

Back to paper searchBrowse research topicsOriginal source
Numerical Simulation Analysis on Vertical Displacement of Step Excavation in Foundation Pit Project — Research Paper | ScholarLens