Technical Performance Based Earned Value as a Management Tool for Engineering Projects

José Ignacio Muñoz Hernández, José-Ramón Otegi-Olaso, Julen Rubio

Open full text 6 citations

Abstract

In the project management, one of the keys for the project success is the control of the project in terms of performance, progress and cost. The first practice to control a project is just checking the financial reporting and therefore the project control is only based on the cost control (budgeted versus actual incurred cost). But the experience, especially from projects that failed, shows that a more efficient project management requires controlling also the project perform‐ ance and scheduling besides the cost.

Open-access reader

About this research paper

What this paper is about

In the project management, one of the keys for the project success is the control of the project in terms of performance, progress and cost. The first practice to control a project is just checking the financial reporting and therefore the project control is only based on the cost control (budgeted versus actual incurred cost). But the experience, especially from projects that failed, shows that a more efficient project management requires controlling also the project perform‐ ance and scheduling besides the cost.

Why it matters

OpenAlex reports 6 citations for this work. Citation counts describe recorded attention and do not establish research quality.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

In the project management, one of the keys for the project success is the control of the project in terms of performance, progress and cost. The first practice to control a project is just checking the financial reporting and therefore the project control is only based on the cost control (budgeted versus actual incurred cost). But the experience, especially from projects that failed, shows that a more efficient project management requires controlling also the project perform‐ ance and scheduling besides the cost.

Key concepts: Earned value management, Project management triangle, Basis of estimate, Project management, Cost engineering, Project planning, Control (management), Engineering management