A COMPUTER PERFORMS ALL LOGIC AND COMPUTATIONS CUSTOMARILY DONE BY HAND IN PREPARATION OF ENGINEER'S ESTIMATES OR CONTRACTOR'S BIDS ON TUNNEL-SHAFT SYSTEMS. THE PROGRAM DESCRIBED IS BASED ON CONSTRUCTION METHODS, WORK FORCES AND EQUIPMENT SELECTIONS CORRESPONDING TO THE CURRENT STATE OF THE ART OF TUNNELING. THE PROGRAM CONTAINS LOGIC TO PERMIT THE ESTIMATE, THE PROGRAM WILL ACCOMMODATE A LARGE NUMBER OF VALUES OR CHANGES IN THE VALUES OF THE FACTORS THAT AFFECT COSTS, SUCH AS TUNNEL SHAPE AND SIZE, SHAFT DEPTH, ROCK CHARACTERISTICS, AND CONSTRUCTION METHOD. TO PROVIDE GREAT FLEXIBILITY, THE USER OF THE PROGRAM IS PROVIDED WITH THE OPTION OF SELECTING LINING TYPE AND THICKNESS, PROFIT AND OVERHEAD MARGINS, AND OTHER INPUT DATA. SUGGESTIONS FOR SELECTING AN APPROPRIATE VALUE FOR THESE INPUTS ARE CONTAINED. COMPLETE OPERATING INSTRUCTIONS AND AN ILLUSTRATIVE EXAMPLE ARE PRESENTED. /AUTHOR/

About this research paper

What this paper is about

A COMPUTER PERFORMS ALL LOGIC AND COMPUTATIONS CUSTOMARILY DONE BY HAND IN PREPARATION OF ENGINEER'S ESTIMATES OR CONTRACTOR'S BIDS ON TUNNEL-SHAFT SYSTEMS. THE PROGRAM DESCRIBED IS BASED ON CONSTRUCTION METHODS, WORK FORCES AND EQUIPMENT SELECTIONS CORRESPONDING TO THE CURRENT STATE OF THE ART OF TUNNELING. THE PROGRAM CONTAINS LOGIC TO PERMIT THE ESTIMATE, THE PROGRAM WILL ACCOMMODATE A LARGE NUMBER OF VALUES OR CHANGES IN THE VALUES OF THE FACTORS THAT AFFECT COSTS, SUCH AS TUNNEL SHAPE AND SIZE, SHAFT DEPTH, ROCK CHARACTERISTICS, AND CONSTRUCTION METHOD. TO PROVIDE GREAT FLEXIBILITY, THE USER OF THE PROGRAM IS PROVIDED WITH THE OPTION OF SELECTING LINING TYPE AND THICKNESS, PROFIT AND OVERHEAD MARGINS, AND OTHER INPUT DATA. SUGGESTIONS FOR SELECTING AN APPROPRIATE VALUE FOR THESE INPUTS ARE CONTAINED. COMPLETE OPERATING INSTRUCTIONS AND AN ILLUSTRATIVE EXAMPLE ARE PRESENTED. /AUTHOR/

Why it matters

OpenAlex reports 1 citations for this work. Citation counts describe recorded attention and do not establish research quality.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

A COMPUTER PERFORMS ALL LOGIC AND COMPUTATIONS CUSTOMARILY DONE BY HAND IN PREPARATION OF ENGINEER'S ESTIMATES OR CONTRACTOR'S BIDS ON TUNNEL-SHAFT SYSTEMS. THE PROGRAM DESCRIBED IS BASED ON CONSTRUCTION METHODS, WORK FORCES AND EQUIPMENT SELECTIONS CORRESPONDING TO THE CURRENT STATE OF THE ART OF TUNNELING. THE PROGRAM CONTAINS LOGIC TO PERMIT THE ESTIMATE, THE PROGRAM WILL ACCOMMODATE A LARGE NUMBER OF VALUES OR CHANGES IN THE VALUES OF THE FACTORS THAT AFFECT COSTS, SUCH AS TUNNEL SHAPE AND SIZE, SHAFT DEPTH, ROCK CHARACTERISTICS, AND CONSTRUCTION METHOD. TO PROVIDE GREAT FLEXIBILITY, THE USER OF THE PROGRAM IS PROVIDED WITH THE OPTION OF SELECTING LINING TYPE AND THICKNESS, PROFIT AND OVERHEAD MARGINS, AND OTHER INPUT DATA. SUGGESTIONS FOR SELECTING AN APPROPRIATE VALUE FOR THESE INPUTS ARE CONTAINED. COMPLETE OPERATING INSTRUCTIONS AND AN ILLUSTRATIVE EXAMPLE ARE PRESENTED. /AUTHOR/

Key concepts: Computer program, Computation, Flexibility (engineering), Computer science, Profit (economics), Overhead (engineering), Engineering, Industrial engineering