1993•Transactions of the American Nuclear SocietyRequires access

Converting the IPE to a full-scope shutdown risk model

Majid Motamed, R.J. Lee, Zoilo S. Roldan, J.H. Ambrose

Open publisher page 0 citations

Abstract

it is now well recognized that conditions occurring during plant shutdown can result in relatively high levels of risk. Southern California Edison (SCE) has for several years sought to manage risks during refueling outages by performing probabilistic evaluations of outage plans using [open quotes]risk-based failure modes and effects analyses[close quotes] to determine the likelihood of both fuel damage and inventory heatup events. In an effort to assess its shutdown risks in as much detail as was done in its recently submitted individual plant examination (IPE), SCE performed a wholesale conversion of its IPE into a full-scope level-1 shutdown probabilistic risk assessment (PRA). With assistance from ERIN Engineering, this effort resulted in a shutdown risk model for the San Onofre nuclear generating station that has become an effective and efficient tool for managing shutdown risk.

About this research paper

What this paper is about

it is now well recognized that conditions occurring during plant shutdown can result in relatively high levels of risk. Southern California Edison (SCE) has for several years sought to manage risks during refueling outages by performing probabilistic evaluations of outage plans using [open quotes]risk-based failure modes and effects analyses[close quotes] to determine the likelihood of both fuel damage and inventory heatup events. In an effort to assess its shutdown risks in as much detail as was done in its recently submitted individual plant examination (IPE), SCE performed a wholesale conversion of its IPE into a full-scope level-1 shutdown probabilistic risk assessment (PRA). With assistance from ERIN Engineering, this effort resulted in a shutdown risk model for the San Onofre nuclear generating station that has become an effective and efficient tool for managing shutdown risk.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

it is now well recognized that conditions occurring during plant shutdown can result in relatively high levels of risk. Southern California Edison (SCE) has for several years sought to manage risks during refueling outages by performing probabilistic evaluations of outage plans using [open quotes]risk-based failure modes and effects analyses[close quotes] to determine the likelihood of both fuel damage and inventory heatup events. In an effort to assess its shutdown risks in as much detail as was done in its recently submitted individual plant examination (IPE), SCE performed a wholesale conversion of its IPE into a full-scope level-1 shutdown probabilistic risk assessment (PRA). With assistance from ERIN Engineering, this effort resulted in a shutdown risk model for the San Onofre nuclear generating station that has become an effective and efficient tool for managing shutdown risk.

Key concepts: Shutdown, Probabilistic risk assessment, Scope (computer science), Probabilistic logic, Nuclear power plant, Engineering, Risk assessment, Risk analysis (engineering)