Strategic oil storage line is completed by H. C. Price Co

D. Dietsch

Open publisher page 0 citations

Abstract

Despite heavy thunderstorms in the area, H. C. Price Co. recently completed its contract to lay 40 mi of 42 in. dia crude oil pipeline for the Strategic Petroleum Reserve Storage program. The line runs from the Sun Oil Co. terminal on the Neches River near Nederland, Tex., to the storage area in West Hackberry, La. The strategic reserve program involves eight storage complexes and 238 mi of large diameter pipeline to connect these sites with terminals or existing pipeline systems. Presently, six sites are located along the gulf coast and two are in the Midwest. The eight storage sites will have a capacity of 412 million bbl, and by Dec. 1978, 150 million bbl will probably be placed in storage. The various storage sites, pipe lengths and sizes, and subcontractors are given and the construction work done by Price is described, including the pipes and the major construction equipment used.

About this research paper

What this paper is about

Despite heavy thunderstorms in the area, H. C. Price Co. recently completed its contract to lay 40 mi of 42 in. dia crude oil pipeline for the Strategic Petroleum Reserve Storage program. The line runs from the Sun Oil Co. terminal on the Neches River near Nederland, Tex., to the storage area in West Hackberry, La. The strategic reserve program involves eight storage complexes and 238 mi of large diameter pipeline to connect these sites with terminals or existing pipeline systems. Presently, six sites are located along the gulf coast and two are in the Midwest. The eight storage sites will have a capacity of 412 million bbl, and by Dec. 1978, 150 million bbl will probably be placed in storage. The various storage sites, pipe lengths and sizes, and subcontractors are given and the construction work done by Price is described, including the pipes and the major construction equipment used.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

Despite heavy thunderstorms in the area, H. C. Price Co. recently completed its contract to lay 40 mi of 42 in. dia crude oil pipeline for the Strategic Petroleum Reserve Storage program. The line runs from the Sun Oil Co. terminal on the Neches River near Nederland, Tex., to the storage area in West Hackberry, La. The strategic reserve program involves eight storage complexes and 238 mi of large diameter pipeline to connect these sites with terminals or existing pipeline systems. Presently, six sites are located along the gulf coast and two are in the Midwest. The eight storage sites will have a capacity of 412 million bbl, and by Dec. 1978, 150 million bbl will probably be placed in storage. The various storage sites, pipe lengths and sizes, and subcontractors are given and the construction work done by Price is described, including the pipes and the major construction equipment used.

Key concepts: Oil storage, Pipeline (software), Pipeline transport, Petroleum, Crude oil, Environmental science, Storage tank, Work (physics)

Related papers

Back to paper searchBrowse research topicsOriginal source
Strategic oil storage line is completed by H. C. Price Co — Research Paper | ScholarLens