1991Unpublished venueRequires access

CHANNEL TUNNEL END IN SIGHT

M Smith

Open publisher page 0 citations

Abstract

This article discusses recent progress in the construction of the Channel Tunnel. Since the initial undersea breakthrough in December 1990 and the completion of the service tunnel in January 1991, the remaining tunnel boring machines have been busy breaking their own records. During the month of March 1991 alone, the four closing marine running tunnel machines completed more than 5.5km. The completion process for the Running Tunnel North started in late April 1991, and for Running Tunnel South a month later. Practical construction of all driven tunnels was expected to be complete nearly half a year ahead of schedule. The UK undersea crossover chamber received its permanent lining of unreinforced concrete, between 900mm and 1200mm thick; the end walls are made of 3.5m thick reinforced concrete. The French are using new methods in the construction of their crossover cavern, the large major civil engineering job on the Channel Tunnel project. Work is progressing well on both the UK and French Terminals, with the construction of overbridges, platforms, permanent buildings, access and egress roads, and tracklaying all well advanced with prospects of completion by the end of 1991.

About this research paper

What this paper is about

This article discusses recent progress in the construction of the Channel Tunnel. Since the initial undersea breakthrough in December 1990 and the completion of the service tunnel in January 1991, the remaining tunnel boring machines have been busy breaking their own records. During the month of March 1991 alone, the four closing marine running tunnel machines completed more than 5.5km. The completion process for the Running Tunnel North started in late April 1991, and for Running Tunnel South a month later. Practical construction of all driven tunnels was expected to be complete nearly half a year ahead of schedule. The UK undersea crossover chamber received its permanent lining of unreinforced concrete, between 900mm and 1200mm thick; the end walls are made of 3.5m thick reinforced concrete. The French are using new methods in the construction of their crossover cavern, the large major civil engineering job on the Channel Tunnel project. Work is progressing well on both the UK and French Terminals, with the construction of overbridges, platforms, permanent buildings, access and egress roads, and tracklaying all well advanced with prospects of completion by the end of 1991.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

This article discusses recent progress in the construction of the Channel Tunnel. Since the initial undersea breakthrough in December 1990 and the completion of the service tunnel in January 1991, the remaining tunnel boring machines have been busy breaking their own records. During the month of March 1991 alone, the four closing marine running tunnel machines completed more than 5.5km. The completion process for the Running Tunnel North started in late April 1991, and for Running Tunnel South a month later. Practical construction of all driven tunnels was expected to be complete nearly half a year ahead of schedule. The UK undersea crossover chamber received its permanent lining of unreinforced concrete, between 900mm and 1200mm thick; the end walls are made of 3.5m thick reinforced concrete. The French are using new methods in the construction of their crossover cavern, the large major civil engineering job on the Channel Tunnel project. Work is progressing well on both the UK and French Terminals, with the construction of overbridges, platforms, permanent buildings, access and egress roads, and tracklaying all well advanced with prospects of completion by the end of 1991.

Key concepts: Channel tunnel, Engineering, Channel (broadcasting), Schedule, Work (physics), Water channel, Telecommunications, Civil engineering

Related papers

Back to paper searchBrowse research topicsOriginal source
CHANNEL TUNNEL END IN SIGHT — Research Paper | ScholarLens