This section of motorway on the North East quadrant of M25 has a very high structural content and includes a cut and cover tunnel 650 m long. The paper describes how the contractor dealt with the general problems of access, programme and construction sequences arising from the location in a heavily-built up urban area, together with certain specific problems. The contract entailed construction of large diaphragm wall panels for both the outer walls of the tunnel and the retaining walls to the east approach. In contrast the retaining walls to the west approach were high modulus steel sheet piles. A large control complex and drainage sump 16 m deep was built adjacent to the tunnel with the excavation stages controlled by the construction of in-situ concrete ring beams. In addition the reinforced earth walls either side of the railway bridge involved the largest area of such walls constructed in the UK. (TRRL)

About this research paper

What this paper is about

This section of motorway on the North East quadrant of M25 has a very high structural content and includes a cut and cover tunnel 650 m long. The paper describes how the contractor dealt with the general problems of access, programme and construction sequences arising from the location in a heavily-built up urban area, together with certain specific problems. The contract entailed construction of large diaphragm wall panels for both the outer walls of the tunnel and the retaining walls to the east approach. In contrast the retaining walls to the west approach were high modulus steel sheet piles. A large control complex and drainage sump 16 m deep was built adjacent to the tunnel with the excavation stages controlled by the construction of in-situ concrete ring beams. In addition the reinforced earth walls either side of the railway bridge involved the largest area of such walls constructed in the UK. (TRRL)

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

This section of motorway on the North East quadrant of M25 has a very high structural content and includes a cut and cover tunnel 650 m long. The paper describes how the contractor dealt with the general problems of access, programme and construction sequences arising from the location in a heavily-built up urban area, together with certain specific problems. The contract entailed construction of large diaphragm wall panels for both the outer walls of the tunnel and the retaining walls to the east approach. In contrast the retaining walls to the west approach were high modulus steel sheet piles. A large control complex and drainage sump 16 m deep was built adjacent to the tunnel with the excavation stages controlled by the construction of in-situ concrete ring beams. In addition the reinforced earth walls either side of the railway bridge involved the largest area of such walls constructed in the UK. (TRRL)

Key concepts: Excavation, Reinforced concrete, Engineering, Structural engineering, Bridge (graph theory), Culvert, Civil engineering, Geotechnical engineering

Related papers

Back to paper searchBrowse research topicsOriginal source
CONSTRUCTION PROBLEMS ON M25(A10-M11) CONTRACT 1 — Research Paper | ScholarLens