1986OSTI OAI (U.S. Department of Energy Office of Scientific and Technical Information)Requires access

Life extension versus modernization: Facts and figures for turbine-generators

Daniel A. Davis, Filippo Vaccaro

Open publisher page 0 citations

Abstract

Due to the high cost of constructing new power plants, today's utility management must make decisions regarding life extension and modernization of mature generating equipment. One of the important decisions to be made is whether to implement basic life extension on turbine-generators or to go a step further and modernize. Turbine-generators with service lives greater than 25-30 years are expected to develop specific reliability concerns such as high temperature rotor material degradation. Modern technology allows for the performance of life evaluations on critical components to predict remaining life and avoid potential forced outages.

About this research paper

What this paper is about

Due to the high cost of constructing new power plants, today's utility management must make decisions regarding life extension and modernization of mature generating equipment. One of the important decisions to be made is whether to implement basic life extension on turbine-generators or to go a step further and modernize. Turbine-generators with service lives greater than 25-30 years are expected to develop specific reliability concerns such as high temperature rotor material degradation. Modern technology allows for the performance of life evaluations on critical components to predict remaining life and avoid potential forced outages.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

Due to the high cost of constructing new power plants, today's utility management must make decisions regarding life extension and modernization of mature generating equipment. One of the important decisions to be made is whether to implement basic life extension on turbine-generators or to go a step further and modernize. Turbine-generators with service lives greater than 25-30 years are expected to develop specific reliability concerns such as high temperature rotor material degradation. Modern technology allows for the performance of life evaluations on critical components to predict remaining life and avoid potential forced outages.

Key concepts: Life extension, Modernization theory, Reliability (semiconductor), Reliability engineering, Turbine, Extension (predicate logic), Rotor (electric), Service life