CONSTRUCTION, PERFORMANCE AND MAINTENANCE OF ROLLER COMPACTED AND OF POURED CONCRETE IN INTERMODAL YARDS AT THE PORT OF TACOMA

Curtis L. Ratcliffe

Open publisher page 0 citations

Abstract

The Port of Tacoma has a North and a South intermodal rail yard. The South yard was constructed in 1985 and was made exclusively of Roller Compacted Concrete (RCC). It covers about 13 acres, was constructed in 120 calendar days, and cost $2 million. The North intermodal yard covers 23 acres and cost $4 million. It has both RCC and cast-in-place surfaces that have performed well. The two yards are operated differently. The South yard uses top picks and the North yard uses straddle carriers. This paper compares the two yards with regard to their method of construction, performance, and maintenance.

About this research paper

What this paper is about

The Port of Tacoma has a North and a South intermodal rail yard. The South yard was constructed in 1985 and was made exclusively of Roller Compacted Concrete (RCC). It covers about 13 acres, was constructed in 120 calendar days, and cost $2 million. The North intermodal yard covers 23 acres and cost $4 million. It has both RCC and cast-in-place surfaces that have performed well. The two yards are operated differently. The South yard uses top picks and the North yard uses straddle carriers. This paper compares the two yards with regard to their method of construction, performance, and maintenance.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

The Port of Tacoma has a North and a South intermodal rail yard. The South yard was constructed in 1985 and was made exclusively of Roller Compacted Concrete (RCC). It covers about 13 acres, was constructed in 120 calendar days, and cost $2 million. The North intermodal yard covers 23 acres and cost $4 million. It has both RCC and cast-in-place surfaces that have performed well. The two yards are operated differently. The South yard uses top picks and the North yard uses straddle carriers. This paper compares the two yards with regard to their method of construction, performance, and maintenance.

Key concepts: Yard, Port (circuit theory), Straddle, Engineering, Civil engineering, Transport engineering, Business, Finance

Related papers

Back to paper searchBrowse research topicsOriginal source
CONSTRUCTION, PERFORMANCE AND MAINTENANCE OF ROLLER COMPACTED AND OF POURED CONCRETE IN INTERMODAL YARDS AT THE PORT OF TACOMA — Research Paper | ScholarLens