SYNTHESIS OF TRAFFIC MANAGEMENT TECHNIQUES FOR MAJOR FREEWAY CONSTRUCTION. INTERIM REPORT

G L Ullman, R A Krammes, C L Dudek

Open publisher page 0 citations

Abstract

This report summarizes the corridor traffic management experiences at completed and ongoing construction projects nationwide. A corridor traffic management plan for a major freeway construction project has three components: (1) the traffic control plan for the construction zone, (2) impact mitigation actions on alternative routes and modes in the corridor, and (3) the public information program. The various strategies and techniques that have been used as part of each component are identified. Data regarding the costs and effectiveness are presented where available. This document will assist highway agencies when developing corridor traffic management plans for major construction projects in the future.

About this research paper

What this paper is about

This report summarizes the corridor traffic management experiences at completed and ongoing construction projects nationwide. A corridor traffic management plan for a major freeway construction project has three components: (1) the traffic control plan for the construction zone, (2) impact mitigation actions on alternative routes and modes in the corridor, and (3) the public information program. The various strategies and techniques that have been used as part of each component are identified. Data regarding the costs and effectiveness are presented where available. This document will assist highway agencies when developing corridor traffic management plans for major construction projects in the future.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

This report summarizes the corridor traffic management experiences at completed and ongoing construction projects nationwide. A corridor traffic management plan for a major freeway construction project has three components: (1) the traffic control plan for the construction zone, (2) impact mitigation actions on alternative routes and modes in the corridor, and (3) the public information program. The various strategies and techniques that have been used as part of each component are identified. Data regarding the costs and effectiveness are presented where available. This document will assist highway agencies when developing corridor traffic management plans for major construction projects in the future.

Key concepts: Interim, Transport engineering, Plan (archaeology), Construction management, Control (management), Engineering, Computer science, Civil engineering