Putnam Street Bridge Replacement

Thomas W Stelmack

Open publisher page 0 citations

Abstract

The Putnam Street Bridge Replacement carries traffic across the Muskingum River in Marietta, Ohio. The low bid on the project was $11.4 million in the spring of 1998. The three-span structure is 69.85 ft. wide-box precast structure built in balanced-cantilever with a longitudinal closure strip between the boxes. The Contractor, Kokosing Construction Co., proposed a Value Engineering Cost Proposal (VECP) to make the structure a single cell, full width cast-in-place box girder based on constructability issues and economics of the design. Parsons, as the Construction Engineers for Kokosing, developed this concept as an alternative, which resulted in a shared savings of $500,000 between Washington County, Ohio and Kokosing.

About this research paper

What this paper is about

The Putnam Street Bridge Replacement carries traffic across the Muskingum River in Marietta, Ohio. The low bid on the project was $11.4 million in the spring of 1998. The three-span structure is 69.85 ft. wide-box precast structure built in balanced-cantilever with a longitudinal closure strip between the boxes. The Contractor, Kokosing Construction Co., proposed a Value Engineering Cost Proposal (VECP) to make the structure a single cell, full width cast-in-place box girder based on constructability issues and economics of the design. Parsons, as the Construction Engineers for Kokosing, developed this concept as an alternative, which resulted in a shared savings of $500,000 between Washington County, Ohio and Kokosing.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

The Putnam Street Bridge Replacement carries traffic across the Muskingum River in Marietta, Ohio. The low bid on the project was $11.4 million in the spring of 1998. The three-span structure is 69.85 ft. wide-box precast structure built in balanced-cantilever with a longitudinal closure strip between the boxes. The Contractor, Kokosing Construction Co., proposed a Value Engineering Cost Proposal (VECP) to make the structure a single cell, full width cast-in-place box girder based on constructability issues and economics of the design. Parsons, as the Construction Engineers for Kokosing, developed this concept as an alternative, which resulted in a shared savings of $500,000 between Washington County, Ohio and Kokosing.

Key concepts: Precast concrete, Constructability, Box girder, Bridge (graph theory), Engineering, Closure (psychology), Span (engineering), Civil engineering

Related papers

Back to paper searchBrowse research topicsOriginal source
Putnam Street Bridge Replacement — Research Paper | ScholarLens