1993Tunnels & tunnellingRequires access

CANOPIED PORTALS FOR NATM RAIL TUNNEL

Amy Mosig Way

Open publisher page 0 citations

Abstract

Construction of a twin-track NATM rail tunnel outside Salzburg in Austria is proceeding according to schedule. The tunnel is being built in loose alluvial sands and gravels which are responding well to the NATM method. Canopies consisting of a primary shotcrete shell reinforced with lattice girders and mesh are being constructed at the portals, the northern one being 45m long to accommodate the weight of two roads which will eventually pass overhead with an overburden of only 1m. (A)

About this research paper

What this paper is about

Construction of a twin-track NATM rail tunnel outside Salzburg in Austria is proceeding according to schedule. The tunnel is being built in loose alluvial sands and gravels which are responding well to the NATM method. Canopies consisting of a primary shotcrete shell reinforced with lattice girders and mesh are being constructed at the portals, the northern one being 45m long to accommodate the weight of two roads which will eventually pass overhead with an overburden of only 1m. (A)

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

Construction of a twin-track NATM rail tunnel outside Salzburg in Austria is proceeding according to schedule. The tunnel is being built in loose alluvial sands and gravels which are responding well to the NATM method. Canopies consisting of a primary shotcrete shell reinforced with lattice girders and mesh are being constructed at the portals, the northern one being 45m long to accommodate the weight of two roads which will eventually pass overhead with an overburden of only 1m. (A)

Key concepts: New Austrian Tunnelling method, Shotcrete, Engineering, Overburden, Roadheader, Girder, Tunnel construction, Excavation