Bridge reconstruction from timber to concrete in 20 working days

W Tabensky

Open publisher page 0 citations

Abstract

The replacement of a timber bridge with a new concrete structure is not new. However, to replace a timber bridge 18.3 m long, 6.7 m wide and 4.5 m high (deck to low water level) using Council's own day labour force without them having had prior concrete bridge construction experience, is quite an achievement. Available funding of $42,000 from VicRoads was considered adequate to complete urgent maintenance works on the bridge sub-structure; however, on removing the timber deck, it was discovered that the structural problems were much more severe and would require extensive repairs to remedy the problem. After an immediate evaluation of the longer term financial benefits to be gained from reconstructing the bridge in preference to costly maintenance repairs, the decision was made to replace the existing timber structure with a new concrete bridge comprising concrete sub-structure, steel stringers and pre-cast concrete decking. Under the supervision and co-ordination of the works by Council's Construction Engineer, Council's day labour employees assigned to this task most effectively completed the reconstruction process in excellent time at a final cost of $134,000.

About this research paper

What this paper is about

The replacement of a timber bridge with a new concrete structure is not new. However, to replace a timber bridge 18.3 m long, 6.7 m wide and 4.5 m high (deck to low water level) using Council's own day labour force without them having had prior concrete bridge construction experience, is quite an achievement. Available funding of $42,000 from VicRoads was considered adequate to complete urgent maintenance works on the bridge sub-structure; however, on removing the timber deck, it was discovered that the structural problems were much more severe and would require extensive repairs to remedy the problem. After an immediate evaluation of the longer term financial benefits to be gained from reconstructing the bridge in preference to costly maintenance repairs, the decision was made to replace the existing timber structure with a new concrete bridge comprising concrete sub-structure, steel stringers and pre-cast concrete decking. Under the supervision and co-ordination of the works by Council's Construction Engineer, Council's day labour employees assigned to this task most effectively completed the reconstruction process in excellent time at a final cost of $134,000.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

The replacement of a timber bridge with a new concrete structure is not new. However, to replace a timber bridge 18.3 m long, 6.7 m wide and 4.5 m high (deck to low water level) using Council's own day labour force without them having had prior concrete bridge construction experience, is quite an achievement. Available funding of $42,000 from VicRoads was considered adequate to complete urgent maintenance works on the bridge sub-structure; however, on removing the timber deck, it was discovered that the structural problems were much more severe and would require extensive repairs to remedy the problem. After an immediate evaluation of the longer term financial benefits to be gained from reconstructing the bridge in preference to costly maintenance repairs, the decision was made to replace the existing timber structure with a new concrete bridge comprising concrete sub-structure, steel stringers and pre-cast concrete decking. Under the supervision and co-ordination of the works by Council's Construction Engineer, Council's day labour employees assigned to this task most effectively completed the reconstruction process in excellent time at a final cost of $134,000.

Key concepts: Bridge (graph theory), Deck, Engineering, Bridge deck, Forensic engineering, Civil engineering, Bridge maintenance, Reinforced concrete

Related papers

Back to paper searchBrowse research topicsOriginal source
Bridge reconstruction from timber to concrete in 20 working days — Research Paper | ScholarLens