With the total number of U.S. bridges approaching 600,000 and the total considered to be substandard approaching 200,000, it is imperative that all components of a bridge work as designed. This is not the case with many bridge deck expansion joint systems. Failure of these systems has resulted in numerous deficiencies such as leaking of deleterious deck chemistry, increased stress levels within the deck system and spalling/cracking adjacent to the joints. In 1983, the Federal Highway Administration enlisted several states to conduct a study on bridge joint performance. This study clearly showed that non-functioning bridge deck joints are a major contributor to premature bridge deterioration which eventually results in the bridge being classified as substandard.

About this research paper

What this paper is about

With the total number of U.S. bridges approaching 600,000 and the total considered to be substandard approaching 200,000, it is imperative that all components of a bridge work as designed. This is not the case with many bridge deck expansion joint systems. Failure of these systems has resulted in numerous deficiencies such as leaking of deleterious deck chemistry, increased stress levels within the deck system and spalling/cracking adjacent to the joints. In 1983, the Federal Highway Administration enlisted several states to conduct a study on bridge joint performance. This study clearly showed that non-functioning bridge deck joints are a major contributor to premature bridge deterioration which eventually results in the bridge being classified as substandard.

Why it matters

OpenAlex reports 1 citations for this work. Citation counts describe recorded attention and do not establish research quality.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

With the total number of U.S. bridges approaching 600,000 and the total considered to be substandard approaching 200,000, it is imperative that all components of a bridge work as designed. This is not the case with many bridge deck expansion joint systems. Failure of these systems has resulted in numerous deficiencies such as leaking of deleterious deck chemistry, increased stress levels within the deck system and spalling/cracking adjacent to the joints. In 1983, the Federal Highway Administration enlisted several states to conduct a study on bridge joint performance. This study clearly showed that non-functioning bridge deck joints are a major contributor to premature bridge deterioration which eventually results in the bridge being classified as substandard.

Key concepts: Spall, Bridge deck, Bridge (graph theory), Deck, Joint (building), Expansion joint, Forensic engineering, Engineering