THE "TOTAL COST" CLAIM: CONTRACTOR'S CURE-ALL OR CURSE?

F Gruebe

Open publisher page 0 citations

Abstract

This article reviews several California cases in which contractors have sued for recovery of breach of contract damages on the basis of total costs incurred in lieu of isolated, precisely defined, well-documented claims. While there is a large body of law permitting the recovery of such damages, the plaintiff contractors ignore not only an equally large number of decisions rejecting the total cost approach which is really intended for extreme cases, but the stringent criteria for permitting total cost recovery. The plaintiff must prove: 1. The nature of the losses makes it impossible or impracticable to determine them with reasonable degree of accuracy. 2. The plaintiff's bid was realistic. 3. The plaintiff's actual costs were reasonable. 4. The plaintiff was not responsible for the added expenses. As a result, the likelihood in most cases is that blanket recovery of huge damages will be rejected for lack of causation. Unfortunately, the courts have been unwilling to do this in the pleasing or pretrial stages, resulting in a burdensome expense to the defendant, i.e. the California taxpayer.

About this research paper

What this paper is about

This article reviews several California cases in which contractors have sued for recovery of breach of contract damages on the basis of total costs incurred in lieu of isolated, precisely defined, well-documented claims. While there is a large body of law permitting the recovery of such damages, the plaintiff contractors ignore not only an equally large number of decisions rejecting the total cost approach which is really intended for extreme cases, but the stringent criteria for permitting total cost recovery. The plaintiff must prove: 1. The nature of the losses makes it impossible or impracticable to determine them with reasonable degree of accuracy. 2. The plaintiff's bid was realistic. 3. The plaintiff's actual costs were reasonable. 4. The plaintiff was not responsible for the added expenses. As a result, the likelihood in most cases is that blanket recovery of huge damages will be rejected for lack of causation. Unfortunately, the courts have been unwilling to do this in the pleasing or pretrial stages, resulting in a burdensome expense to the defendant, i.e. the California taxpayer.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

This article reviews several California cases in which contractors have sued for recovery of breach of contract damages on the basis of total costs incurred in lieu of isolated, precisely defined, well-documented claims. While there is a large body of law permitting the recovery of such damages, the plaintiff contractors ignore not only an equally large number of decisions rejecting the total cost approach which is really intended for extreme cases, but the stringent criteria for permitting total cost recovery. The plaintiff must prove: 1. The nature of the losses makes it impossible or impracticable to determine them with reasonable degree of accuracy. 2. The plaintiff's bid was realistic. 3. The plaintiff's actual costs were reasonable. 4. The plaintiff was not responsible for the added expenses. As a result, the likelihood in most cases is that blanket recovery of huge damages will be rejected for lack of causation. Unfortunately, the courts have been unwilling to do this in the pleasing or pretrial stages, resulting in a burdensome expense to the defendant, i.e. the California taxpayer.

Key concepts: Plaintiff, Damages, Causation, Taxpayer, Breach of contract, Actuarial science, Business, Law