CAPACITY AND TRAFFIC CHARACTERISTICS AT A FREEWAY WORK ZONE IN FINLAND
A Enberg, M S Mannan
Abstract
A Enberg, M S Mannan
Abstract
This paper deals with traffic flow characteristics and capacity of a work zone on one of the main freeways in southern Finland. The speed limit was 50 km/h. Point measurements with portable Hi-Star Counters and car following studies using an instrumented vehicle were done. The speed level at the work zone was 30-65 km/h in the morning peak towards east and 35-65 km/h in the evening peak towards west. The spacing between the leading vehicle and the following vehicle varied between 5 and 30 m and the mode was about 12 m. The space mean speeds were found to be a little lower than the speed limit in peak hour traffic but higher than the speed limit in normal traffic. The calculated capacity was 1,636 veh/h for the basic lane and 1,828 veh/h for the passing lane and 1,828 veh/h for the passing lane towards east.
OpenAlex reports 4 citations for this work. Citation counts describe recorded attention and do not establish research quality.
A contribution statement is not available in the OpenAlex record.
Method details are not available in the OpenAlex metadata.
Findings are not separately available in the OpenAlex metadata.
Limitations are not available in the OpenAlex metadata.
Application details are not available in the OpenAlex metadata.
This paper deals with traffic flow characteristics and capacity of a work zone on one of the main freeways in southern Finland. The speed limit was 50 km/h. Point measurements with portable Hi-Star Counters and car following studies using an instrumented vehicle were done. The speed level at the work zone was 30-65 km/h in the morning peak towards east and 35-65 km/h in the evening peak towards west. The spacing between the leading vehicle and the following vehicle varied between 5 and 30 m and the mode was about 12 m. The space mean speeds were found to be a little lower than the speed limit in peak hour traffic but higher than the speed limit in normal traffic. The calculated capacity was 1,636 veh/h for the basic lane and 1,828 veh/h for the passing lane and 1,828 veh/h for the passing lane towards east.
Key concepts: Speed limit, Traffic flow (computer networking), Work zone, Work (physics), Morning, Meteorology, Evening, Limit (mathematics)