2023IEEE Transactions on Power DeliveryRequires access

A Prioritization Method for Switchgear Maintenance Based on Equipment Failure Mode Analysis and Integrated Risk Assessment

Nan Zhou, Yan Xu

Open publisher page 25 citations

Abstract

Switchgear is one of the key equipment in power grids. A proper maintenance strategy maximizes the cost-efficiency of switchgear maintenance expenses, meanwhile minimizing the power grid failure risk. Existing maintenance strategies that seldom consider the interconnected relation among different components in a power equipment are not applicable to switchgear which comprises of various moving and fixed parts and components. In this article, a prioritization method is proposed for medium voltage switchgear maintenance based on equipment failure mode analysis and power grid failure risk assessment. Failure mode analysis is first performed to analyze the interconnection between switchgear components and its failure mechanisms, giving a more accurate failure probability prediction result. An integrated risk assessment method is then developed to analyze the impact of switchgear failure on both the power grid losses and the cost-efficiency of maintenance activities. Based on that, the maintenance priority can be determined in a cost-efficient manner. Case studies are performed on the data of a 12 kV substation. Compared to time-based maintenance strategies, the proposed method achieves a 38% increase in cost-efficiency.

About this research paper

What this paper is about

Switchgear is one of the key equipment in power grids. A proper maintenance strategy maximizes the cost-efficiency of switchgear maintenance expenses, meanwhile minimizing the power grid failure risk. Existing maintenance strategies that seldom consider the interconnected relation among different components in a power equipment are not applicable to switchgear which comprises of various moving and fixed parts and components. In this article, a prioritization method is proposed for medium voltage switchgear maintenance based on equipment failure mode analysis and power grid failure risk assessment. Failure mode analysis is first performed to analyze the interconnection between switchgear components and its failure mechanisms, giving a more accurate failure probability prediction result. An integrated risk assessment method is then developed to analyze the impact of switchgear failure on both the power grid losses and the cost-efficiency of maintenance activities. Based on that, the maintenance priority can be determined in a cost-efficient manner. Case studies are performed on the data of a 12 kV substation. Compared to time-based maintenance strategies, the proposed method achieves a 38% increase in cost-efficiency.

Why it matters

OpenAlex reports 25 citations for this work. Citation counts describe recorded attention and do not establish research quality.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

Switchgear is one of the key equipment in power grids. A proper maintenance strategy maximizes the cost-efficiency of switchgear maintenance expenses, meanwhile minimizing the power grid failure risk. Existing maintenance strategies that seldom consider the interconnected relation among different components in a power equipment are not applicable to switchgear which comprises of various moving and fixed parts and components. In this article, a prioritization method is proposed for medium voltage switchgear maintenance based on equipment failure mode analysis and power grid failure risk assessment. Failure mode analysis is first performed to analyze the interconnection between switchgear components and its failure mechanisms, giving a more accurate failure probability prediction result. An integrated risk assessment method is then developed to analyze the impact of switchgear failure on both the power grid losses and the cost-efficiency of maintenance activities. Based on that, the maintenance priority can be determined in a cost-efficient manner. Case studies are performed on the data of a 12 kV substation. Compared to time-based maintenance strategies, the proposed method achieves a 38% increase in cost-efficiency.

Key concepts: Switchgear, Reliability engineering, Failure mode and effects analysis, Prioritization, Maintenance engineering, Engineering, Risk analysis (engineering), Risk assessment