2023Operations Management ResearchOpen access

Straightening machine preventive maintenance intervention plan based on AHP: a case study in a steel company in Brazil

Uálison Rébula de Oliveira, Hilda Anatiely Donato de Souza, Carlos Augusto Gabriel Menezes, Henrique Martins Rocha

Open full text 9 citations

Abstract

Equipment failure and production shortfalls can cause significant impacts on companies. Preventive maintenance can potentially increase equipment reliability and availability, helping companies achieve their corporate goals while reducing operation and maintenance costs. However, determining the optimal interval between maintenance interventions involves balancing various factors such as maintenance costs, equipment availability, risk of failures, and the need for corrective maintenance, as well as potential operational and financial impacts. Under this context, this paper aims to define the interval between preventive maintenance interventions for a key production equipment in a steel company located in Southeast region of Brazil. Upon documental analysis and interviews with experts, an AHP was applied to hierarchize the maintenance periodicity, based on the following criteria: part replacement based on service life, downtime hours for preventive maintenance, equipment reliability, and cost of materials and labour. A biweekly preventive maintenance periodicity was identified as the most adequate for the analysed device. An implementation plan was approved and preliminary results indicate no availability deterioration, while maintenance costs are below historical average.

Open-access reader

About this research paper

What this paper is about

Equipment failure and production shortfalls can cause significant impacts on companies. Preventive maintenance can potentially increase equipment reliability and availability, helping companies achieve their corporate goals while reducing operation and maintenance costs. However, determining the optimal interval between maintenance interventions involves balancing various factors such as maintenance costs, equipment availability, risk of failures, and the need for corrective maintenance, as well as potential operational and financial impacts. Under this context, this paper aims to define the interval between preventive maintenance interventions for a key production equipment in a steel company located in Southeast region of Brazil. Upon documental analysis and interviews with experts, an AHP was applied to hierarchize the maintenance periodicity, based on the following criteria: part replacement based on service life, downtime hours for preventive maintenance, equipment reliability, and cost of materials and labour. A biweekly preventive maintenance periodicity was identified as the most adequate for the analysed device. An implementation plan was approved and preliminary results indicate no availability deterioration, while maintenance costs are below historical average.

Why it matters

OpenAlex reports 9 citations for this work. Citation counts describe recorded attention and do not establish research quality.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

Equipment failure and production shortfalls can cause significant impacts on companies. Preventive maintenance can potentially increase equipment reliability and availability, helping companies achieve their corporate goals while reducing operation and maintenance costs. However, determining the optimal interval between maintenance interventions involves balancing various factors such as maintenance costs, equipment availability, risk of failures, and the need for corrective maintenance, as well as potential operational and financial impacts. Under this context, this paper aims to define the interval between preventive maintenance interventions for a key production equipment in a steel company located in Southeast region of Brazil. Upon documental analysis and interviews with experts, an AHP was applied to hierarchize the maintenance periodicity, based on the following criteria: part replacement based on service life, downtime hours for preventive maintenance, equipment reliability, and cost of materials and labour. A biweekly preventive maintenance periodicity was identified as the most adequate for the analysed device. An implementation plan was approved and preliminary results indicate no availability deterioration, while maintenance costs are below historical average.

Key concepts: Preventive maintenance, Planned maintenance, Downtime, Corrective maintenance, Proactive maintenance, Reliability (semiconductor), Context (archaeology), Operations management