2022The Journal of Development StudiesOpen access

Optimism Bias and World Bank Project Performance

Lavagnon A. Ika, Simon Feeny

Open full text 16 citations

Abstract

This paper examines the correlates of optimism bias and its impact on World Bank project performance. We measure optimism bias in different ways using estimated Economic Rates of Return (ERR) of projects at approval and closure. We examine over 2,800 World Bank projects that were appraised between 1960 and 2019. We find that approximately 60% of projects in the sample were prone to optimism bias. Correlates of optimism bias include both project and country characteristics. Findings also indicate that the incidence of optimism bias reduces the chance of a satisfactory project performance rate at the time of evaluation by 17–20%. Recommendations include embracing complexity and uncertainty in considering projects for approval, providing organizational incentives for ensuring projects are successful rather than ERRs being accurate, shifting some resources from appraisal to implementation, and changing the nature of project supervision.

About this research paper

What this paper is about

This paper examines the correlates of optimism bias and its impact on World Bank project performance. We measure optimism bias in different ways using estimated Economic Rates of Return (ERR) of projects at approval and closure. We examine over 2,800 World Bank projects that were appraised between 1960 and 2019. We find that approximately 60% of projects in the sample were prone to optimism bias. Correlates of optimism bias include both project and country characteristics. Findings also indicate that the incidence of optimism bias reduces the chance of a satisfactory project performance rate at the time of evaluation by 17–20%. Recommendations include embracing complexity and uncertainty in considering projects for approval, providing organizational incentives for ensuring projects are successful rather than ERRs being accurate, shifting some resources from appraisal to implementation, and changing the nature of project supervision.

Why it matters

OpenAlex reports 16 citations for this work. Citation counts describe recorded attention and do not establish research quality.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

This paper examines the correlates of optimism bias and its impact on World Bank project performance. We measure optimism bias in different ways using estimated Economic Rates of Return (ERR) of projects at approval and closure. We examine over 2,800 World Bank projects that were appraised between 1960 and 2019. We find that approximately 60% of projects in the sample were prone to optimism bias. Correlates of optimism bias include both project and country characteristics. Findings also indicate that the incidence of optimism bias reduces the chance of a satisfactory project performance rate at the time of evaluation by 17–20%. Recommendations include embracing complexity and uncertainty in considering projects for approval, providing organizational incentives for ensuring projects are successful rather than ERRs being accurate, shifting some resources from appraisal to implementation, and changing the nature of project supervision.

Key concepts: Optimism, Optimism bias, Incentive, Project appraisal, Actuarial science, Economics, Sample (material), Accounting