1982Nordisk BetongRequires access

THE NEW TJOERN BRIDGE

S Rickne, Christian Franklin Svensson

Open publisher page 0 citations

Abstract

On the 18th January 1980 an off-course bulk carrier collided with the Tjoern Bridge, bringing the arch span and the deck slab down into the water. On the 19th June, Skanska was appointed contractor, and on the 9th November 1981, the new bridge was opened for traffic. The entire project has taken no more than half the time normally required for the construction of a structure this size. The new bridge is a cable stayed bridge with concrete pylons, a 366 M long main span of steel, and concrete approaches. The design and construction are briefly described in this article. (TRRL)

About this research paper

What this paper is about

On the 18th January 1980 an off-course bulk carrier collided with the Tjoern Bridge, bringing the arch span and the deck slab down into the water. On the 19th June, Skanska was appointed contractor, and on the 9th November 1981, the new bridge was opened for traffic. The entire project has taken no more than half the time normally required for the construction of a structure this size. The new bridge is a cable stayed bridge with concrete pylons, a 366 M long main span of steel, and concrete approaches. The design and construction are briefly described in this article. (TRRL)

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

On the 18th January 1980 an off-course bulk carrier collided with the Tjoern Bridge, bringing the arch span and the deck slab down into the water. On the 19th June, Skanska was appointed contractor, and on the 9th November 1981, the new bridge was opened for traffic. The entire project has taken no more than half the time normally required for the construction of a structure this size. The new bridge is a cable stayed bridge with concrete pylons, a 366 M long main span of steel, and concrete approaches. The design and construction are briefly described in this article. (TRRL)

Key concepts: Bridge (graph theory), Span (engineering), Deck, Engineering, Arch bridge, Beam bridge, Forensic engineering, Slab