1995Highways and transportationRequires access

DEVELOPMENT OF THE SECOND SEVERN CROSSING

N. Haste

Open publisher page 0 citations

Abstract

This paper describes the design and construction of the Second Severn Crossing, which is three miles downstream of the existing Severn Bridge between England and Wales. In October 1990, the Government signed a formal Concession Agreement with Severn River Crossing Plc to lease and maintain the existing bridge, design and construct the new bridge, and operate and maintain both bridges for up to 30 years. The narrow shipping channel and difficult geographical conditions there led to a bridge design, which includes a cable-stayed bridge with 456m central span, linked to the banks of the Severn by two long multi-span approach viaducts. Before preparing the design, it was decided to: (1) minimise the amount of work to be done in the river; (2) maximise the prefabrication or precasting and modularisation of as many bridge components as practicable; and (3) base construction methods on the extensive use of jack-up barges or self-elevating platforms. The concrete caisson shells for the foundations are up to 350m by 13m by 13m and weigh up to 2000t; they were filled with concrete after placing. The central bridge pylons and viaduct piers are made of concrete. The steel deck sections are pre-assembled on-shore.

About this research paper

What this paper is about

This paper describes the design and construction of the Second Severn Crossing, which is three miles downstream of the existing Severn Bridge between England and Wales. In October 1990, the Government signed a formal Concession Agreement with Severn River Crossing Plc to lease and maintain the existing bridge, design and construct the new bridge, and operate and maintain both bridges for up to 30 years. The narrow shipping channel and difficult geographical conditions there led to a bridge design, which includes a cable-stayed bridge with 456m central span, linked to the banks of the Severn by two long multi-span approach viaducts. Before preparing the design, it was decided to: (1) minimise the amount of work to be done in the river; (2) maximise the prefabrication or precasting and modularisation of as many bridge components as practicable; and (3) base construction methods on the extensive use of jack-up barges or self-elevating platforms. The concrete caisson shells for the foundations are up to 350m by 13m by 13m and weigh up to 2000t; they were filled with concrete after placing. The central bridge pylons and viaduct piers are made of concrete. The steel deck sections are pre-assembled on-shore.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

This paper describes the design and construction of the Second Severn Crossing, which is three miles downstream of the existing Severn Bridge between England and Wales. In October 1990, the Government signed a formal Concession Agreement with Severn River Crossing Plc to lease and maintain the existing bridge, design and construct the new bridge, and operate and maintain both bridges for up to 30 years. The narrow shipping channel and difficult geographical conditions there led to a bridge design, which includes a cable-stayed bridge with 456m central span, linked to the banks of the Severn by two long multi-span approach viaducts. Before preparing the design, it was decided to: (1) minimise the amount of work to be done in the river; (2) maximise the prefabrication or precasting and modularisation of as many bridge components as practicable; and (3) base construction methods on the extensive use of jack-up barges or self-elevating platforms. The concrete caisson shells for the foundations are up to 350m by 13m by 13m and weigh up to 2000t; they were filled with concrete after placing. The central bridge pylons and viaduct piers are made of concrete. The steel deck sections are pre-assembled on-shore.

Key concepts: Bridge (graph theory), Deck, Span (engineering), Engineering, Civil engineering, Caisson, Shore, Channel (broadcasting)

Related papers

Back to paper searchBrowse research topicsOriginal source
DEVELOPMENT OF THE SECOND SEVERN CROSSING — Research Paper | ScholarLens