2004CONCRETERequires access

TIME SAVING TECHNOLOGY SUCCEEDS FOR FAIRFIELD UNDERPASS

Derek Thornhill

Open publisher page 0 citations

Abstract

The 28-m Fairfield Underpass was built under the A507 trunk road in Stotfold, Bedfordshire to provide a link for pedestrians and cyclists between the town and a new development on the south side of the town. Geoffrey Osborne won the contract with an innovative approach that cut 12 weeks off the schedule and confined traffic disruption to just one weekend. The entire structure of precast concrete sections was built in a purpose-built casting pit to one side of the road and then driven into position over the weekend closure. The structure was built using EFCO tunnel formwork and specialist multi-axle trailer systems (Sarens' SPMT units). Details are given of the underpass design, formwork strategy, and construction logistics.

About this research paper

What this paper is about

The 28-m Fairfield Underpass was built under the A507 trunk road in Stotfold, Bedfordshire to provide a link for pedestrians and cyclists between the town and a new development on the south side of the town. Geoffrey Osborne won the contract with an innovative approach that cut 12 weeks off the schedule and confined traffic disruption to just one weekend. The entire structure of precast concrete sections was built in a purpose-built casting pit to one side of the road and then driven into position over the weekend closure. The structure was built using EFCO tunnel formwork and specialist multi-axle trailer systems (Sarens' SPMT units). Details are given of the underpass design, formwork strategy, and construction logistics.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

The 28-m Fairfield Underpass was built under the A507 trunk road in Stotfold, Bedfordshire to provide a link for pedestrians and cyclists between the town and a new development on the south side of the town. Geoffrey Osborne won the contract with an innovative approach that cut 12 weeks off the schedule and confined traffic disruption to just one weekend. The entire structure of precast concrete sections was built in a purpose-built casting pit to one side of the road and then driven into position over the weekend closure. The structure was built using EFCO tunnel formwork and specialist multi-axle trailer systems (Sarens' SPMT units). Details are given of the underpass design, formwork strategy, and construction logistics.

Key concepts: Precast concrete, Formwork, Stairs, Schedule, Engineering, Transport engineering, Civil engineering, Forensic engineering

Related papers

Back to paper searchBrowse research topicsOriginal source
TIME SAVING TECHNOLOGY SUCCEEDS FOR FAIRFIELD UNDERPASS — Research Paper | ScholarLens