Investigating the Factors Affecting Delays in Infrastructure Projects

Anurup Kakkar, Prakhar Duggal

Open full text 1 citations

Abstract

Time and expense overruns are regular occurrences in the construction industry all around the world but these are a major concern in developing countries such as India, and their consequences can be extremely harmful when public infrastructure projects are concerned. In India as per the MoS & PI report, as of October 2019, there were 552 delayed construction projects, and the mean time overrun in these 552 delayed projects is29.07 months. Many studies in the literature review previously, have concentrated on a variety of infrastructure risk management issues but there have only been a few studies that have looked into the overall dynamics of infrastructure and how a project's timeline can be affected by changing risk interactions. This article aids in the investigation of the variables and causes of construction delays in infrastructure projects.

About this research paper

What this paper is about

Time and expense overruns are regular occurrences in the construction industry all around the world but these are a major concern in developing countries such as India, and their consequences can be extremely harmful when public infrastructure projects are concerned. In India as per the MoS & PI report, as of October 2019, there were 552 delayed construction projects, and the mean time overrun in these 552 delayed projects is29.07 months. Many studies in the literature review previously, have concentrated on a variety of infrastructure risk management issues but there have only been a few studies that have looked into the overall dynamics of infrastructure and how a project's timeline can be affected by changing risk interactions. This article aids in the investigation of the variables and causes of construction delays in infrastructure projects.

Why it matters

OpenAlex reports 1 citations for this work. Citation counts describe recorded attention and do not establish research quality.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

Time and expense overruns are regular occurrences in the construction industry all around the world but these are a major concern in developing countries such as India, and their consequences can be extremely harmful when public infrastructure projects are concerned. In India as per the MoS & PI report, as of October 2019, there were 552 delayed construction projects, and the mean time overrun in these 552 delayed projects is29.07 months. Many studies in the literature review previously, have concentrated on a variety of infrastructure risk management issues but there have only been a few studies that have looked into the overall dynamics of infrastructure and how a project's timeline can be affected by changing risk interactions. This article aids in the investigation of the variables and causes of construction delays in infrastructure projects.

Key concepts: Timeline, Critical infrastructure, Variety (cybernetics), Business, Public infrastructure, Cost overrun, Transportation infrastructure, Project management