National Dam Inspection Program. Gorson Dam (NDI ID Number PA-01084, DER ID Number 52-61, Delaware River Basin, Mill Creek, Pike County, Pennsylvania. Phase I Inspection Report,

Frederick Futchko

Open publisher page 0 citations

Abstract

Based on the criteria established for these studies, Gorson Dam is judged to be unsafe, nonemergency, because the spillway capacity is seriously inadequate. The recommended Spillway Design Flood (SDF) for the size and hazard classification of the dam varies between 1/2 of the Probable Maximum Flood (PMF) and the PMF. The selected SDF is the 1/2 PMF. The existing spillway will pass only about 20 percent of the PMF before overtopping of the dam occurs. It is judged that the dam could not withstand the depth and duration of overtopping that would occur for the 1/2 PMF. If the low areas on the top of the dam were filled to the design elevation, the spillway would pass about 36 percent of the PMF without any overtopping. For either condition, the spillway capacity is rated as seriously inadequate. Failure of Gorson Dam would cause an increased hazard for loss of life downstream.

About this research paper

What this paper is about

Based on the criteria established for these studies, Gorson Dam is judged to be unsafe, nonemergency, because the spillway capacity is seriously inadequate. The recommended Spillway Design Flood (SDF) for the size and hazard classification of the dam varies between 1/2 of the Probable Maximum Flood (PMF) and the PMF. The selected SDF is the 1/2 PMF. The existing spillway will pass only about 20 percent of the PMF before overtopping of the dam occurs. It is judged that the dam could not withstand the depth and duration of overtopping that would occur for the 1/2 PMF. If the low areas on the top of the dam were filled to the design elevation, the spillway would pass about 36 percent of the PMF without any overtopping. For either condition, the spillway capacity is rated as seriously inadequate. Failure of Gorson Dam would cause an increased hazard for loss of life downstream.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

Based on the criteria established for these studies, Gorson Dam is judged to be unsafe, nonemergency, because the spillway capacity is seriously inadequate. The recommended Spillway Design Flood (SDF) for the size and hazard classification of the dam varies between 1/2 of the Probable Maximum Flood (PMF) and the PMF. The selected SDF is the 1/2 PMF. The existing spillway will pass only about 20 percent of the PMF before overtopping of the dam occurs. It is judged that the dam could not withstand the depth and duration of overtopping that would occur for the 1/2 PMF. If the low areas on the top of the dam were filled to the design elevation, the spillway would pass about 36 percent of the PMF without any overtopping. For either condition, the spillway capacity is rated as seriously inadequate. Failure of Gorson Dam would cause an increased hazard for loss of life downstream.

Key concepts: Spillway, Dam failure, Hydrology (agriculture), Flood myth, Environmental science, Detention basin, Flooding (psychology), Geotechnical engineering

Related papers

Back to paper searchBrowse research topicsOriginal source
National Dam Inspection Program. Gorson Dam (NDI ID Number PA-01084, DER ID Number 52-61, Delaware River Basin, Mill Creek, Pike County, Pennsylvania. Phase I Inspection Report, — Research Paper | ScholarLens