Observed Performance of Highway Embankment over Soft Marine Clay: A Case Study in Wenzhou, China
Xia Bian, Jinkai Yan, Wei Zhang
Abstract
Open-access reader
Xia Bian, Jinkai Yan, Wei Zhang
Abstract
Open-access reader
This paper presents a case history of observed performance of highway embankment over soft marine clay in Wenzhou, China. During the embankment construction, the changes of ground settlement, ground displacement, and lateral displacement of subsoil with the construction time were monitored and analyzed. The monitoring results indicate that the ground settlement and lateral displacement of subsoil account for about 75% in the process of embankment construction. The measured maximum values of ground settlement, ground displacement, and lateral displacement of subsoil are 37.88 mm, 21.50 mm, and 23.56 mm, respectively. After the completion of the embankment construction, the settlement gradually tended to be stable. It is suggested that the monitoring data of settlement and displacement of embankment are smaller than the design requirements, and the embankment stability is also ensured.
OpenAlex reports 6 citations for this work. Citation counts describe recorded attention and do not establish research quality.
A contribution statement is not available in the OpenAlex record.
Method details are not available in the OpenAlex metadata.
Findings are not separately available in the OpenAlex metadata.
Limitations are not available in the OpenAlex metadata.
Application details are not available in the OpenAlex metadata.
This paper presents a case history of observed performance of highway embankment over soft marine clay in Wenzhou, China. During the embankment construction, the changes of ground settlement, ground displacement, and lateral displacement of subsoil with the construction time were monitored and analyzed. The monitoring results indicate that the ground settlement and lateral displacement of subsoil account for about 75% in the process of embankment construction. The measured maximum values of ground settlement, ground displacement, and lateral displacement of subsoil are 37.88 mm, 21.50 mm, and 23.56 mm, respectively. After the completion of the embankment construction, the settlement gradually tended to be stable. It is suggested that the monitoring data of settlement and displacement of embankment are smaller than the design requirements, and the embankment stability is also ensured.
Key concepts: Subsoil, Levee, Geotechnical engineering, Settlement (finance), Displacement (psychology), Geology, Soil water, Soil science