LOOKAHEAD PLANNING: THE MISSING LINK IN PRODUCTION CONTROL

Glenn Ballard

Open publisher page 175 citations

Abstract

Lookahead planning is one of the decision functions that constitute production control systems (Melles and Wamelink 1993). It stands between overall project coordination schedules and short term crew-level commitments, screening out scheduled activities that should but cannot be done and improving the success rate of completing the tasks assigned in weekly and daily plans. When measured against such objectives, current industry lookahead planning is poorly performed. A case study is presented to illustrate current procedures and performance, and suggestions are offered for improvement. Preface

About this research paper

What this paper is about

Lookahead planning is one of the decision functions that constitute production control systems (Melles and Wamelink 1993). It stands between overall project coordination schedules and short term crew-level commitments, screening out scheduled activities that should but cannot be done and improving the success rate of completing the tasks assigned in weekly and daily plans. When measured against such objectives, current industry lookahead planning is poorly performed. A case study is presented to illustrate current procedures and performance, and suggestions are offered for improvement. Preface

Why it matters

OpenAlex reports 175 citations for this work. Citation counts describe recorded attention and do not establish research quality.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

Lookahead planning is one of the decision functions that constitute production control systems (Melles and Wamelink 1993). It stands between overall project coordination schedules and short term crew-level commitments, screening out scheduled activities that should but cannot be done and improving the success rate of completing the tasks assigned in weekly and daily plans. When measured against such objectives, current industry lookahead planning is poorly performed. A case study is presented to illustrate current procedures and performance, and suggestions are offered for improvement. Preface

Key concepts: Crew, Production (economics), Control (management), Production planning, Operations research, Term (time), Operations management, Computer science