Field monitoring on deformation of high rock slope during highway construction: A case study in Wenzhou, China
Yaqiong Wang, Shaobing Zhang, Longlong Chen, Yongli Xie, Zhifeng Wang
Abstract
Yaqiong Wang, Shaobing Zhang, Longlong Chen, Yongli Xie, Zhifeng Wang
Abstract
In order to study the deformation stability of rock slope during the excavation of cutting slope and ensure the safety of rock slope during construction and operation period, this article analyzed the deformation law of a typical slope excavation by monitoring the surface deformation and the internal displacement of the rock mass. The surface deformation of the slope is monitored by setting monitoring points, and the internal deformation of the slope is monitored by installing multipoint displacement meters and inclinometers. Therefore, the relationship between slope excavation and deformation is obtained. The analysis of monitoring results shows that the slope is stable before excavation, and the displacement of the slope is gradually increased with the slope excavation. After the excavation, the displacement of each slope tends to converge. The maximum displacement in surface monitoring points is 12.30 mm, and the displacement parallels to the direction of the expressway. The maximum vertical displacement in surface monitoring points is 10.60 mm which occurred in the third step; the maximum internal displacement is 11.02 mm which mainly occurs in the weak structural plane of the rock boundary. During the excavation of the weak rock slope, the slope rock mass is prone to large displacement deformation. After the excavation, the slope surface displacement and internal displacement tend to converge in a short time.
OpenAlex reports 21 citations for this work. Citation counts describe recorded attention and do not establish research quality.
A contribution statement is not available in the OpenAlex record.
Method details are not available in the OpenAlex metadata.
Findings are not separately available in the OpenAlex metadata.
Limitations are not available in the OpenAlex metadata.
Application details are not available in the OpenAlex metadata.
In order to study the deformation stability of rock slope during the excavation of cutting slope and ensure the safety of rock slope during construction and operation period, this article analyzed the deformation law of a typical slope excavation by monitoring the surface deformation and the internal displacement of the rock mass. The surface deformation of the slope is monitored by setting monitoring points, and the internal deformation of the slope is monitored by installing multipoint displacement meters and inclinometers. Therefore, the relationship between slope excavation and deformation is obtained. The analysis of monitoring results shows that the slope is stable before excavation, and the displacement of the slope is gradually increased with the slope excavation. After the excavation, the displacement of each slope tends to converge. The maximum displacement in surface monitoring points is 12.30 mm, and the displacement parallels to the direction of the expressway. The maximum vertical displacement in surface monitoring points is 10.60 mm which occurred in the third step; the maximum internal displacement is 11.02 mm which mainly occurs in the weak structural plane of the rock boundary. During the excavation of the weak rock slope, the slope rock mass is prone to large displacement deformation. After the excavation, the slope surface displacement and internal displacement tend to converge in a short time.
Key concepts: Excavation, Displacement (psychology), Inclinometer, Geology, Deformation (meteorology), Geotechnical engineering, Rock mass classification, Slope stability