Interim Report on Masonboro Inlet, North Carolina, Movable-Bed Model Tests

Noel W. Hollyfield

Open publisher page 0 citations

Abstract

The movable-bed model study of Masonboro Inlet was undertaken to evaluate model predictions of inlet response to a major improvement project when verification is based on preconstruction conditions. Masonboro Inlet was chosen for the study because prototype survey data were available for the preconstruction condition of the inlet area, and hydrographic surveys had been performed at approximately six-month intervals subsequent to construction of the north jetty. The initial plan of study was to verify the model for the prejetty prototype data, install the north jetty, then operate the model for the period necessary to simulate the passage of time to the date of the latest hydrographic survey. Model results were to be compared to the prototype data to ascertain how well the model predicted the bed changes that occurred in nature. Only two of the four prototype prejetty hydrographic surveys were usable for model adjustment and verification. The time interval between the surveys was nine months (from the end of October 1964 to the first of August 1965). This nine-month interval was not adequate for model verification since there was insufficient change in the inlet hydrography to provide a satisfactory verification data base.

About this research paper

What this paper is about

The movable-bed model study of Masonboro Inlet was undertaken to evaluate model predictions of inlet response to a major improvement project when verification is based on preconstruction conditions. Masonboro Inlet was chosen for the study because prototype survey data were available for the preconstruction condition of the inlet area, and hydrographic surveys had been performed at approximately six-month intervals subsequent to construction of the north jetty. The initial plan of study was to verify the model for the prejetty prototype data, install the north jetty, then operate the model for the period necessary to simulate the passage of time to the date of the latest hydrographic survey. Model results were to be compared to the prototype data to ascertain how well the model predicted the bed changes that occurred in nature. Only two of the four prototype prejetty hydrographic surveys were usable for model adjustment and verification. The time interval between the surveys was nine months (from the end of October 1964 to the first of August 1965). This nine-month interval was not adequate for model verification since there was insufficient change in the inlet hydrography to provide a satisfactory verification data base.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

The movable-bed model study of Masonboro Inlet was undertaken to evaluate model predictions of inlet response to a major improvement project when verification is based on preconstruction conditions. Masonboro Inlet was chosen for the study because prototype survey data were available for the preconstruction condition of the inlet area, and hydrographic surveys had been performed at approximately six-month intervals subsequent to construction of the north jetty. The initial plan of study was to verify the model for the prejetty prototype data, install the north jetty, then operate the model for the period necessary to simulate the passage of time to the date of the latest hydrographic survey. Model results were to be compared to the prototype data to ascertain how well the model predicted the bed changes that occurred in nature. Only two of the four prototype prejetty hydrographic surveys were usable for model adjustment and verification. The time interval between the surveys was nine months (from the end of October 1964 to the first of August 1965). This nine-month interval was not adequate for model verification since there was insufficient change in the inlet hydrography to provide a satisfactory verification data base.

Key concepts: Inlet, Interim, Environmental science, Geology, Geography, Geomorphology, Archaeology

Related papers

Back to paper searchBrowse research topicsOriginal source
Interim Report on Masonboro Inlet, North Carolina, Movable-Bed Model Tests — Research Paper | ScholarLens