Risk Management in Indonesia Construction Project: A Case Study of a Toll Road Project
Mochammad Agung Wibowo, Jati Utomo Dwi Hatmoko, Asri Nurdiana
Abstract
Open-access reader
Mochammad Agung Wibowo, Jati Utomo Dwi Hatmoko, Asri Nurdiana
Abstract
Open-access reader
While project risks are generally acknowledged merely from owner and contractor perspectives, other parties also play important roles in the project. The aim of this study is to analyze the application of risk management in the toll road project from stakeholders’ perception, such as contractor, owner, design consultant, supervisory consultant, and community surrounding the project. Data of risk factors were collected through interviews with each stakeholder, including the probability of occurrence and their impacts. Risk Breakdown Structure (RBS) has been adapted to breakdown project risks from various stakeholders. Risk level of each risk factor is obtained by multiplying the probability and the impact. The overall results of risk analysis show various risks as perceived by each stakeholder due to different roles and interests in the project. This research provides an understanding of how project risks need to be fully comprehended for the success of the project.
OpenAlex reports 6 citations for this work. Citation counts describe recorded attention and do not establish research quality.
A contribution statement is not available in the OpenAlex record.
Method details are not available in the OpenAlex metadata.
Findings are not separately available in the OpenAlex metadata.
Limitations are not available in the OpenAlex metadata.
Application details are not available in the OpenAlex metadata.
While project risks are generally acknowledged merely from owner and contractor perspectives, other parties also play important roles in the project. The aim of this study is to analyze the application of risk management in the toll road project from stakeholders’ perception, such as contractor, owner, design consultant, supervisory consultant, and community surrounding the project. Data of risk factors were collected through interviews with each stakeholder, including the probability of occurrence and their impacts. Risk Breakdown Structure (RBS) has been adapted to breakdown project risks from various stakeholders. Risk level of each risk factor is obtained by multiplying the probability and the impact. The overall results of risk analysis show various risks as perceived by each stakeholder due to different roles and interests in the project. This research provides an understanding of how project risks need to be fully comprehended for the success of the project.
Key concepts: Project risk management, Risk management plan, Project sponsorship, Stakeholder, Risk management, Business, Toll road, Project stakeholder