Application of Blasingame Type Curves to a Multi-Well Gas-Condensate Reservoir: Field Case Study

P. M. Adrian, Marcia Ruth Cabrera

Open publisher page 3 citations

Abstract

Abstract Nowadays advanced decline curve analysis techniques are widely accepted for estimating Hydrocarbon Initially in place (HCIIP), reservoir parameters and production forecasting. These analytical techniques were developed assuming different reservoir models and wellbore geometries. Most of them considered an ideal single well reservoir system, which is not a common scenario of production. In light of that, some authors have proposed theoretical solutions for the analysis of production data of multi-well reservoir. Gas and oil reservoirs has been studied and validated with reservoir simulation models; however the application to real field case was not addresses in detail. There is an example for gas-condensate reservoir with the multi-well approach and the other for an oil field by applying a single well methodology. This paper presents a field case study application of Blasingame type curve method to a multi-well gas-condensate reservoir. Total material balance pseudo-time was calculated using the two-phase compressibility factor. Bottomhole flowing pressures were calculated with vertical flow correlations and adjusted with dynamic gradients. A single well production data was analyzed to estimate the total Original Gas In-Place of a gas-condensate reservoir as well as reservoir parameters. The results of the multi-well method were comparable with volumetric and conventional material balance estimations, as well as well testing interpretation results. Therefore the reliability of the multi-well type curve approach to gas-condensate reservoirs was confirmed.

About this research paper

What this paper is about

Abstract Nowadays advanced decline curve analysis techniques are widely accepted for estimating Hydrocarbon Initially in place (HCIIP), reservoir parameters and production forecasting. These analytical techniques were developed assuming different reservoir models and wellbore geometries. Most of them considered an ideal single well reservoir system, which is not a common scenario of production. In light of that, some authors have proposed theoretical solutions for the analysis of production data of multi-well reservoir. Gas and oil reservoirs has been studied and validated with reservoir simulation models; however the application to real field case was not addresses in detail. There is an example for gas-condensate reservoir with the multi-well approach and the other for an oil field by applying a single well methodology. This paper presents a field case study application of Blasingame type curve method to a multi-well gas-condensate reservoir. Total material balance pseudo-time was calculated using the two-phase compressibility factor. Bottomhole flowing pressures were calculated with vertical flow correlations and adjusted with dynamic gradients. A single well production data was analyzed to estimate the total Original Gas In-Place of a gas-condensate reservoir as well as reservoir parameters. The results of the multi-well method were comparable with volumetric and conventional material balance estimations, as well as well testing interpretation results. Therefore the reliability of the multi-well type curve approach to gas-condensate reservoirs was confirmed.

Why it matters

OpenAlex reports 3 citations for this work. Citation counts describe recorded attention and do not establish research quality.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

Abstract Nowadays advanced decline curve analysis techniques are widely accepted for estimating Hydrocarbon Initially in place (HCIIP), reservoir parameters and production forecasting. These analytical techniques were developed assuming different reservoir models and wellbore geometries. Most of them considered an ideal single well reservoir system, which is not a common scenario of production. In light of that, some authors have proposed theoretical solutions for the analysis of production data of multi-well reservoir. Gas and oil reservoirs has been studied and validated with reservoir simulation models; however the application to real field case was not addresses in detail. There is an example for gas-condensate reservoir with the multi-well approach and the other for an oil field by applying a single well methodology. This paper presents a field case study application of Blasingame type curve method to a multi-well gas-condensate reservoir. Total material balance pseudo-time was calculated using the two-phase compressibility factor. Bottomhole flowing pressures were calculated with vertical flow correlations and adjusted with dynamic gradients. A single well production data was analyzed to estimate the total Original Gas In-Place of a gas-condensate reservoir as well as reservoir parameters. The results of the multi-well method were comparable with volumetric and conventional material balance estimations, as well as well testing interpretation results. Therefore the reliability of the multi-well type curve approach to gas-condensate reservoirs was confirmed.

Key concepts: Petroleum engineering, Reservoir engineering, Natural gas field, Reservoir modeling, Reservoir simulation, Material balance, Oil field, Reliability (semiconductor)

Related papers

Back to paper searchBrowse research topicsOriginal source
Application of Blasingame Type Curves to a Multi-Well Gas-Condensate Reservoir: Field Case Study — Research Paper | ScholarLens