2017•Organization Technology and Management in Construction An International JournalOpen access

Cost and time performance of traditional-, direct labour- and management-procured public projects in Ondo State, Nigeria

Douglas Omoregie Aghimien, Olufemi Osanyinro, Taiwo Fadeke Adegbembo

Open full text 4 citations

Abstract

Abstract Procurement method over time has proven to have significant influence on the successful delivery of construction projects. Making the right decision in the selection of a procurement option to adopt is therefore crucial if a project is to succeed. This study therefore assessed the cost and time performance of selected public building projects procured using traditional, direct labour and management procurement options in Ondo State, Nigeria. A pro forma was used to gather cost and time data from government procuring entities in the state. In addition, a structured questionnaire was used to obtain information from construction professionals in these procuring entities, in order to ascertain the factors influencing the choice of procurement options adopted. The cost and time data gathered were analyzed using percentages and the paired-samples t-test, while those gathered on the factors influencing the choice of procurement options were analyzed using mean item scores and analysis of variance (ANOVA). The results revealed that although there is no significant difference between the initial and final costs of the assessed projects, some measure of cost overrun still exists. In addition, a considerable amount of time overrun was experienced on projects executed using the three different procurement options. The most significant factors influencing the choice of a procurement option are price competition, speed, time certainty and complexity of the project. It is believed that the findings of this study will provide public procuring entities with insight on the cost and time capability of these procurement methods and aid them in selecting the procurement option that will help in delivering public building projects within the budget and on schedule.

Open-access reader

About this research paper

What this paper is about

Abstract Procurement method over time has proven to have significant influence on the successful delivery of construction projects. Making the right decision in the selection of a procurement option to adopt is therefore crucial if a project is to succeed. This study therefore assessed the cost and time performance of selected public building projects procured using traditional, direct labour and management procurement options in Ondo State, Nigeria. A pro forma was used to gather cost and time data from government procuring entities in the state. In addition, a structured questionnaire was used to obtain information from construction professionals in these procuring entities, in order to ascertain the factors influencing the choice of procurement options adopted. The cost and time data gathered were analyzed using percentages and the paired-samples t-test, while those gathered on the factors influencing the choice of procurement options were analyzed using mean item scores and analysis of variance (ANOVA). The results revealed that although there is no significant difference between the initial and final costs of the assessed projects, some measure of cost overrun still exists. In addition, a considerable amount of time overrun was experienced on projects executed using the three different procurement options. The most significant factors influencing the choice of a procurement option are price competition, speed, time certainty and complexity of the project. It is believed that the findings of this study will provide public procuring entities with insight on the cost and time capability of these procurement methods and aid them in selecting the procurement option that will help in delivering public building projects within the budget and on schedule.

Why it matters

OpenAlex reports 4 citations for this work. Citation counts describe recorded attention and do not establish research quality.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

Abstract Procurement method over time has proven to have significant influence on the successful delivery of construction projects. Making the right decision in the selection of a procurement option to adopt is therefore crucial if a project is to succeed. This study therefore assessed the cost and time performance of selected public building projects procured using traditional, direct labour and management procurement options in Ondo State, Nigeria. A pro forma was used to gather cost and time data from government procuring entities in the state. In addition, a structured questionnaire was used to obtain information from construction professionals in these procuring entities, in order to ascertain the factors influencing the choice of procurement options adopted. The cost and time data gathered were analyzed using percentages and the paired-samples t-test, while those gathered on the factors influencing the choice of procurement options were analyzed using mean item scores and analysis of variance (ANOVA). The results revealed that although there is no significant difference between the initial and final costs of the assessed projects, some measure of cost overrun still exists. In addition, a considerable amount of time overrun was experienced on projects executed using the three different procurement options. The most significant factors influencing the choice of a procurement option are price competition, speed, time certainty and complexity of the project. It is believed that the findings of this study will provide public procuring entities with insight on the cost and time capability of these procurement methods and aid them in selecting the procurement option that will help in delivering public building projects within the budget and on schedule.

Key concepts: Procurement, Business, Cost overrun, Government (linguistics), Operations management, Order (exchange), Risk analysis (engineering), Finance