SCHEDULE PLANNING AND MANAGEMENT WITH MILESTONE IN REPETITIVE CONSTRUCTION WORK

Hiroaki Nagaoka, Shuzo Furusaka, Hyeong Geun Park, Takashi Kaneta

Open full text 2 citations

Abstract

Milestone is often used in repetitive construction work. This paper describes adaptation of milestone to scheduling technique. Milestone can be applied in two ways. In the first way, manpower coordination is checked and changed according to the probability of achievement at the next milestone, while the one at the final milestone is considered in the second way. Scheduling application on a sample project is shown to evaluate the probability of achievement and working ratio. It can be concluded that milestone is effective in schedule management, whose two methods are developed in this paper.

Open-access reader

About this research paper

What this paper is about

Milestone is often used in repetitive construction work. This paper describes adaptation of milestone to scheduling technique. Milestone can be applied in two ways. In the first way, manpower coordination is checked and changed according to the probability of achievement at the next milestone, while the one at the final milestone is considered in the second way. Scheduling application on a sample project is shown to evaluate the probability of achievement and working ratio. It can be concluded that milestone is effective in schedule management, whose two methods are developed in this paper.

Why it matters

OpenAlex reports 2 citations for this work. Citation counts describe recorded attention and do not establish research quality.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

Milestone is often used in repetitive construction work. This paper describes adaptation of milestone to scheduling technique. Milestone can be applied in two ways. In the first way, manpower coordination is checked and changed according to the probability of achievement at the next milestone, while the one at the final milestone is considered in the second way. Scheduling application on a sample project is shown to evaluate the probability of achievement and working ratio. It can be concluded that milestone is effective in schedule management, whose two methods are developed in this paper.

Key concepts: Milestone, Schedule, Scheduling (production processes), Computer science, Work (physics), Engineering management, Engineering, Operations management