Problems of shield tunneling for Beijing Metro and solutions

Xinjin Zhang, Weining Liu, Meili Lu

Open publisher page 0 citations

Abstract

Based on a detailed investigation and analysis, the present situation of shield tunneling for Beijing metro construction was studied. The main problems of shield method in the planning of the projects were as follows. First, continuous tunnel sections constructed by shield method were only a few; second, the efficiency of shield machine was low; third, the time used for non-driving tasks in shield tunneling was too long; fourth, the construction period using shield tunneling could not be guaranteed; and finally, the additional cost of shield tunneling was high. Detailed analysis indicates that the major cause for the problems was the contradiction of construction time between shield tunnel sections and adjoining stations, with the additional cause being that construction organization of shield tunneling was not well planned, that is the problem of shield machine passing the station was not well solved. A solution to the problems was put forward: let the shield machine pass a series of stations in the line first, and then construct the stations by cut-and-cover method or mining method at proper times. Such scheme shows great advantages in improving the quality, increasing the speed and reducing the cost of metro construction.

About this research paper

What this paper is about

Based on a detailed investigation and analysis, the present situation of shield tunneling for Beijing metro construction was studied. The main problems of shield method in the planning of the projects were as follows. First, continuous tunnel sections constructed by shield method were only a few; second, the efficiency of shield machine was low; third, the time used for non-driving tasks in shield tunneling was too long; fourth, the construction period using shield tunneling could not be guaranteed; and finally, the additional cost of shield tunneling was high. Detailed analysis indicates that the major cause for the problems was the contradiction of construction time between shield tunnel sections and adjoining stations, with the additional cause being that construction organization of shield tunneling was not well planned, that is the problem of shield machine passing the station was not well solved. A solution to the problems was put forward: let the shield machine pass a series of stations in the line first, and then construct the stations by cut-and-cover method or mining method at proper times. Such scheme shows great advantages in improving the quality, increasing the speed and reducing the cost of metro construction.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

Based on a detailed investigation and analysis, the present situation of shield tunneling for Beijing metro construction was studied. The main problems of shield method in the planning of the projects were as follows. First, continuous tunnel sections constructed by shield method were only a few; second, the efficiency of shield machine was low; third, the time used for non-driving tasks in shield tunneling was too long; fourth, the construction period using shield tunneling could not be guaranteed; and finally, the additional cost of shield tunneling was high. Detailed analysis indicates that the major cause for the problems was the contradiction of construction time between shield tunnel sections and adjoining stations, with the additional cause being that construction organization of shield tunneling was not well planned, that is the problem of shield machine passing the station was not well solved. A solution to the problems was put forward: let the shield machine pass a series of stations in the line first, and then construct the stations by cut-and-cover method or mining method at proper times. Such scheme shows great advantages in improving the quality, increasing the speed and reducing the cost of metro construction.

Key concepts: Shield, Beijing, Quantum tunnelling, Line (geometry), Engineering, Civil engineering, Computer science, Geology

Related papers

Back to paper searchBrowse research topicsOriginal source
Problems of shield tunneling for Beijing Metro and solutions — Research Paper | ScholarLens