1982Sov. Power Eng. (Engl. Transl.); (United States)Requires access

Experience in the introduction of proximate testing of boiler units in the Belglavenergo power system

A.A. Apanovich, V. P. Parfenov, P.D. Korotkin

Open publisher page 0 citations

Abstract

The testing of steam generator units for the Belglavenergo power system is discussed. The organization and systematic operation of a well-planned program for testing these units is not a complex measure. The program permits objective criteria on the actual condition of the equipment to be obtained in any period of operation with minimal cost.

About this research paper

What this paper is about

The testing of steam generator units for the Belglavenergo power system is discussed. The organization and systematic operation of a well-planned program for testing these units is not a complex measure. The program permits objective criteria on the actual condition of the equipment to be obtained in any period of operation with minimal cost.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

The testing of steam generator units for the Belglavenergo power system is discussed. The organization and systematic operation of a well-planned program for testing these units is not a complex measure. The program permits objective criteria on the actual condition of the equipment to be obtained in any period of operation with minimal cost.

Key concepts: Boiler (water heating), Reliability engineering, Engineering, Computer science, Waste management

Related papers

Back to paper searchBrowse research topicsOriginal source
Experience in the introduction of proximate testing of boiler units in the Belglavenergo power system — Research Paper | ScholarLens