2007China Harbour EngineeringRequires access

Design of Head of Deep Water Breakwater (Jetty)

Sun Hao-cang

Open publisher page 0 citations

Abstract

The deepwater breakwater(concurrently a jetty)matching for Huaxia angxi Power Station of Guangdong shall be built by two(2)stages,i.e.Stage No.1 and Stage No.2.The head of the breakwater shall adopt a vertical wall plugging structure in Stage No.1.This type of the structure is suitable to deepwater breakwater(jetty)suffering from effect of heavy wave force from multi-directions.At the same time,this structure can shorten construction period,reduce costs,and it is a good structure form.

About this research paper

What this paper is about

The deepwater breakwater(concurrently a jetty)matching for Huaxia angxi Power Station of Guangdong shall be built by two(2)stages,i.e.Stage No.1 and Stage No.2.The head of the breakwater shall adopt a vertical wall plugging structure in Stage No.1.This type of the structure is suitable to deepwater breakwater(jetty)suffering from effect of heavy wave force from multi-directions.At the same time,this structure can shorten construction period,reduce costs,and it is a good structure form.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

The deepwater breakwater(concurrently a jetty)matching for Huaxia angxi Power Station of Guangdong shall be built by two(2)stages,i.e.Stage No.1 and Stage No.2.The head of the breakwater shall adopt a vertical wall plugging structure in Stage No.1.This type of the structure is suitable to deepwater breakwater(jetty)suffering from effect of heavy wave force from multi-directions.At the same time,this structure can shorten construction period,reduce costs,and it is a good structure form.

Key concepts: Jetty, Breakwater, Stage (stratigraphy), Head (geology), Deep water, Geotechnical engineering, Tsunami wave, Geology

Related papers

Back to paper searchBrowse research topicsOriginal source
Design of Head of Deep Water Breakwater (Jetty) — Research Paper | ScholarLens