TECHNOLOGY OF PREVENTING DEVIATION TO DRILL VERTICALLY IN WELL PUGUANG 3

De Jin

Open publisher page 0 citations

Abstract

The top stratum of Puguang 3 well belongs to highly steep structure, and its obliquity is big which result in borehole deviation. Drillability of the stratum is poor, and bit bouncing is severe. Preventing borehole deviation to drill vertical well of the top stratum are difficulties of constructions. During drilling, pendulum drill assembly, tower type make - up of string composed of large diameter drill collars and screw drill tool were applied in the well. Application effect showed that bit pressure was required small to prevent borehole deviation when pendulum make - up of string was used in the surface layer, which restricted drilling speed; tower type make ?up of string composed of large diameter drill collars had a better effect on preventing borehole deviation, and it could effectively improve the drilling speed when matching with suitable drilling parameters and optimizing selection drill bit type, screw torque make - up of string was a more active measurement of preventing borehole deviation which is necessary to be further explored.

About this research paper

What this paper is about

The top stratum of Puguang 3 well belongs to highly steep structure, and its obliquity is big which result in borehole deviation. Drillability of the stratum is poor, and bit bouncing is severe. Preventing borehole deviation to drill vertical well of the top stratum are difficulties of constructions. During drilling, pendulum drill assembly, tower type make - up of string composed of large diameter drill collars and screw drill tool were applied in the well. Application effect showed that bit pressure was required small to prevent borehole deviation when pendulum make - up of string was used in the surface layer, which restricted drilling speed; tower type make ?up of string composed of large diameter drill collars had a better effect on preventing borehole deviation, and it could effectively improve the drilling speed when matching with suitable drilling parameters and optimizing selection drill bit type, screw torque make - up of string was a more active measurement of preventing borehole deviation which is necessary to be further explored.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

The top stratum of Puguang 3 well belongs to highly steep structure, and its obliquity is big which result in borehole deviation. Drillability of the stratum is poor, and bit bouncing is severe. Preventing borehole deviation to drill vertical well of the top stratum are difficulties of constructions. During drilling, pendulum drill assembly, tower type make - up of string composed of large diameter drill collars and screw drill tool were applied in the well. Application effect showed that bit pressure was required small to prevent borehole deviation when pendulum make - up of string was used in the surface layer, which restricted drilling speed; tower type make ?up of string composed of large diameter drill collars had a better effect on preventing borehole deviation, and it could effectively improve the drilling speed when matching with suitable drilling parameters and optimizing selection drill bit type, screw torque make - up of string was a more active measurement of preventing borehole deviation which is necessary to be further explored.

Key concepts: Borehole, Drill, Drilling, Drill string, Stratum, Drill bit, Geology, Pendulum