Research on Gas Drainage Roadway Layout for Outburst Coal Seam Floor Rock

Huiyu Wang

Open publisher page 0 citations

Abstract

Regional pre- pumping must be done before mining in outburst coal seam,only after the residual gas pressure and gas content decreased to 0.74 MPa and 8 m3/t below,it could begin mining.Taking 32206 working face of Shanxi Shangliang Coal Mine as the background,it studied and analyzed the distribution of floor rock pre- pumping roadway in outburst coal seam group.With the numerical simulation of the software RFPA,it found out the new stress distribution after the outburst coal seam mining,which should be the location of small stress impact and closest to the next coal seam.It made sure that the maintenance of roadway was easy and the construction distance of pre- pumping drilling could be short so as to save time and money.

About this research paper

What this paper is about

Regional pre- pumping must be done before mining in outburst coal seam,only after the residual gas pressure and gas content decreased to 0.74 MPa and 8 m3/t below,it could begin mining.Taking 32206 working face of Shanxi Shangliang Coal Mine as the background,it studied and analyzed the distribution of floor rock pre- pumping roadway in outburst coal seam group.With the numerical simulation of the software RFPA,it found out the new stress distribution after the outburst coal seam mining,which should be the location of small stress impact and closest to the next coal seam.It made sure that the maintenance of roadway was easy and the construction distance of pre- pumping drilling could be short so as to save time and money.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

Regional pre- pumping must be done before mining in outburst coal seam,only after the residual gas pressure and gas content decreased to 0.74 MPa and 8 m3/t below,it could begin mining.Taking 32206 working face of Shanxi Shangliang Coal Mine as the background,it studied and analyzed the distribution of floor rock pre- pumping roadway in outburst coal seam group.With the numerical simulation of the software RFPA,it found out the new stress distribution after the outburst coal seam mining,which should be the location of small stress impact and closest to the next coal seam.It made sure that the maintenance of roadway was easy and the construction distance of pre- pumping drilling could be short so as to save time and money.

Key concepts: Drilling, Coal mining, Coal, Mining engineering, Problems in coal mining, Drainage, Gas pressure, Geology

Related papers

Back to paper searchBrowse research topicsOriginal source
Research on Gas Drainage Roadway Layout for Outburst Coal Seam Floor Rock — Research Paper | ScholarLens