2008•Yangtze RiverRequires access

Prestressed anchor-bar construction in spillway tunnel of Xiluodu hydropower station on right bank

Deng Liang-chao

Open publisher page 0 citations

Abstract

For prestressed anchor- bar construction, the construction technology requirement is high, the working procedures link up closely, and the requirement on the working area is also high in construction. The working area of spillway tunnel of Xiluodu hydropower station on the right bank is narrow, resulting in difficult construction. In order to guarantee construction quality and progress, tentative production was carried out before formal construction, construction methods were compared and selected and the suitable construction parameters were determined. In the construction, some parameters related with machinery platform, various equipments, material were adjusted for further optimization of prestressed anchor-bar construction.

About this research paper

What this paper is about

For prestressed anchor- bar construction, the construction technology requirement is high, the working procedures link up closely, and the requirement on the working area is also high in construction. The working area of spillway tunnel of Xiluodu hydropower station on the right bank is narrow, resulting in difficult construction. In order to guarantee construction quality and progress, tentative production was carried out before formal construction, construction methods were compared and selected and the suitable construction parameters were determined. In the construction, some parameters related with machinery platform, various equipments, material were adjusted for further optimization of prestressed anchor-bar construction.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

For prestressed anchor- bar construction, the construction technology requirement is high, the working procedures link up closely, and the requirement on the working area is also high in construction. The working area of spillway tunnel of Xiluodu hydropower station on the right bank is narrow, resulting in difficult construction. In order to guarantee construction quality and progress, tentative production was carried out before formal construction, construction methods were compared and selected and the suitable construction parameters were determined. In the construction, some parameters related with machinery platform, various equipments, material were adjusted for further optimization of prestressed anchor-bar construction.

Key concepts: Hydropower, Spillway, Engineering, Bar (unit), Civil engineering, Geotechnical engineering, Geology, Electrical engineering