It analyzed the seepage control effect in large scale seepage-prevention wall under high lateral seepage condition by assuming the duration of flood peak,basing the theory of unsaturated and unsteady seepage theory,and using the FEM numerical model.According to Geological Survey report,two programs of the cement cut-off wall,with the depth of 10 meter and 15 meter,were calculated and analyzed.With the seepage-control effects of the two programs,mainly about the seepage discharge,the seepage velocity,changes in saturation line and so on,the optimal wall depth was selected.

About this research paper

What this paper is about

It analyzed the seepage control effect in large scale seepage-prevention wall under high lateral seepage condition by assuming the duration of flood peak,basing the theory of unsaturated and unsteady seepage theory,and using the FEM numerical model.According to Geological Survey report,two programs of the cement cut-off wall,with the depth of 10 meter and 15 meter,were calculated and analyzed.With the seepage-control effects of the two programs,mainly about the seepage discharge,the seepage velocity,changes in saturation line and so on,the optimal wall depth was selected.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

It analyzed the seepage control effect in large scale seepage-prevention wall under high lateral seepage condition by assuming the duration of flood peak,basing the theory of unsaturated and unsteady seepage theory,and using the FEM numerical model.According to Geological Survey report,two programs of the cement cut-off wall,with the depth of 10 meter and 15 meter,were calculated and analyzed.With the seepage-control effects of the two programs,mainly about the seepage discharge,the seepage velocity,changes in saturation line and so on,the optimal wall depth was selected.

Key concepts: Geotechnical engineering, Geology, Metre, Saturation (graph theory), Finite element method, Engineering, Structural engineering, Mathematics

Related papers

Back to paper searchBrowse research topicsOriginal source
Research on Seepage-Prevention Wall Design of Large Canal Slope under High Lateral Seepage — Research Paper | ScholarLens