Total time and critical path simulation on flexible network plan

Jiang Xiao-dong

Open publisher page 0 citations

Abstract

Traditional plan,with the duration for every activity being fixed,is not suitable for actual construction management,because in actual project cases,the duration of every activity varies with many occasional factors.A model called flexible network is put forward.Flexible network,simulating the random variation of the duration of every activity,can reveal the scope of total time and the probability of certain activity on Critical Path.On the basis of the model,the paper studies the algrithem of Monte Carlo for computer simulation and a rather practical program is developed with Microsoft Visual Basic.NET 2005 Beta.

About this research paper

What this paper is about

Traditional plan,with the duration for every activity being fixed,is not suitable for actual construction management,because in actual project cases,the duration of every activity varies with many occasional factors.A model called flexible network is put forward.Flexible network,simulating the random variation of the duration of every activity,can reveal the scope of total time and the probability of certain activity on Critical Path.On the basis of the model,the paper studies the algrithem of Monte Carlo for computer simulation and a rather practical program is developed with Microsoft Visual Basic.NET 2005 Beta.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

Traditional plan,with the duration for every activity being fixed,is not suitable for actual construction management,because in actual project cases,the duration of every activity varies with many occasional factors.A model called flexible network is put forward.Flexible network,simulating the random variation of the duration of every activity,can reveal the scope of total time and the probability of certain activity on Critical Path.On the basis of the model,the paper studies the algrithem of Monte Carlo for computer simulation and a rather practical program is developed with Microsoft Visual Basic.NET 2005 Beta.

Key concepts: Critical path method, Duration (music), Scope (computer science), Computer science, Path (computing), Plan (archaeology), Monte Carlo method, Basis (linear algebra)