Causes Analysis on Seepage of Newly Built Dam of Tibet Jiangxiong Reservoir and Treatment

Zhu Jia-wang

Open publisher page 0 citations

Abstract

At initial impoundment period,the water level in observation hole became high,the seepage amount was gradually increasing at the downstream of Jiangxiong reservoir dam and the abnormal phenomena appeared with maximum seepage amount of 300 L/s at the measuring weir,which affect the dam safety.Analysis was made on the major seepage causes of dam foundation,around-the-dam,spillway and water intake tunnel by dam observation system,electricity detection and interconnection test,the main seepage channels found to provide decision basis for dam impermeable scheme.And a view is also presented in this paper that safe seepage has enormous function to protect downstream ecology.

About this research paper

What this paper is about

At initial impoundment period,the water level in observation hole became high,the seepage amount was gradually increasing at the downstream of Jiangxiong reservoir dam and the abnormal phenomena appeared with maximum seepage amount of 300 L/s at the measuring weir,which affect the dam safety.Analysis was made on the major seepage causes of dam foundation,around-the-dam,spillway and water intake tunnel by dam observation system,electricity detection and interconnection test,the main seepage channels found to provide decision basis for dam impermeable scheme.And a view is also presented in this paper that safe seepage has enormous function to protect downstream ecology.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

At initial impoundment period,the water level in observation hole became high,the seepage amount was gradually increasing at the downstream of Jiangxiong reservoir dam and the abnormal phenomena appeared with maximum seepage amount of 300 L/s at the measuring weir,which affect the dam safety.Analysis was made on the major seepage causes of dam foundation,around-the-dam,spillway and water intake tunnel by dam observation system,electricity detection and interconnection test,the main seepage channels found to provide decision basis for dam impermeable scheme.And a view is also presented in this paper that safe seepage has enormous function to protect downstream ecology.

Key concepts: Spillway, Embankment dam, Foundation (evidence), Geotechnical engineering, Dam break, Dam removal, Geology, Hydrology (agriculture)