Study on Approach to Optimize Network Planning Schedule for Fixed Resources Constraint

WU Zhen-ye

Open publisher page 1 citations

Abstract

Network planning schedule optimization is one of the pivotal issues in engineering project management.The current studies on schedule optimization aim at achieving the optimal goals by least additional resources.In this paper,from transferring the critical path,the authors suggest a schedule optimization algorithm through transferring partial resource of un-critical activities to the critical activities.The result of applying the model shows that it is helpful for resolving schedule optimization issue for fixed resources.

About this research paper

What this paper is about

Network planning schedule optimization is one of the pivotal issues in engineering project management.The current studies on schedule optimization aim at achieving the optimal goals by least additional resources.In this paper,from transferring the critical path,the authors suggest a schedule optimization algorithm through transferring partial resource of un-critical activities to the critical activities.The result of applying the model shows that it is helpful for resolving schedule optimization issue for fixed resources.

Why it matters

OpenAlex reports 1 citations for this work. Citation counts describe recorded attention and do not establish research quality.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

Network planning schedule optimization is one of the pivotal issues in engineering project management.The current studies on schedule optimization aim at achieving the optimal goals by least additional resources.In this paper,from transferring the critical path,the authors suggest a schedule optimization algorithm through transferring partial resource of un-critical activities to the critical activities.The result of applying the model shows that it is helpful for resolving schedule optimization issue for fixed resources.

Key concepts: Schedule, Critical path method, Computer science, Constraint (computer-aided design), Operations research, Mathematical optimization, Network planning and design, Engineering